How To Exam?

a knowledge trading engine...


University of Mumbai 2008 Post Graduate Diploma SYPGDORM Part - II - Advance Operation Reserch I - Question Paper

Wednesday, 17 July 2013 08:15Web


Kindly obtain the attachment.

5. y. Drpfoma >y>    pcec\rcW Marf. acc,

Pajperin:- /VHwy>fe OpevxMioo Re.crrc'kl CFov f/mm-e. nrwv. may")nf    

-08.    '    BB-8593 1


Con. 2175 & (a)(b)-08.


[ Total Marks : 100


N.B. : (1)    Answer any five questions.

(2)    Figures to the right indicate full marks.

(3)    Use of Statistical Tables and Non-Programmable calculator is permitted.

(4)    Answers must be brief and to the points.

(5)    Intermediate explanations and calculations must be given.

(6)    Assumptions, wherever necessary, must be clearly stated.


1. (a) Solve the following LPP using Branch and Bound Algorithm :


Maximize Z = x1 + x2


subject to 2x1 + 5x2 < 16, 6x1 + 5x2< 30,

x1 and x2are non-negative integers, (b) Solve the following LPP by Dual Simplex Method Minimize Z = 4x1 + 3x2


Subject to xt + 3x2>


-x1 + 2x2 > 20 x1f x2, > 0


P<3_p0t3?l?0/


Mna ! -07 595


to 8595


3 Hours )


10


10


30


Solve the following parametric programming problem : Maximize z = 3x1 + 2x2+ 5x3 subject to x1 + 2x2 + x3 < 30 - 7t

10


2. (a)


< 60 + 2t < 40 - t


3x, + 2x3

X1 + 4X2 t > 0


X,, x2, x3,


10


(b) Write down the Dual Problem for the following LPP subject to


Minimize Z = 5x1 + 3x2- 4x3


+ x3> 5


X1 + X2>


2x, - 5x2 + x3 = 6

x1( x2 > 0 and x3 is unrestricted


10


Solve the following problem by Revised Simplex method Minimize Z = 42x1 + 45x2 + 40x3 Subject to x1 + 3x2 + 4x3> 3

2


3. (a)


2x1 +


2x2 + 4x3 >


x. + 2x, + 4x > 5, x2, x3> 0

10


(b) The following information gives distances in kms between 6 cities A, B, C, D, E, F.

Draw the Spanning Tree.

4.    Determine an optimum solution for the following LPP :    20

Maximize Z = 25x1 + 6x2 + 8x3 subject to 2x1+4x2-3x3 < 30 x1 + 3x2 + x3 < 25 x1f x2, x? > 0.

(a)    Find the change in the optimum solution if

c1 changes from 25 to 30

(b)    If a new contraint, x1 + 2x2- x3< 30 is added find the new optimum solution.

(c)    If the RHS of the constraints changes from (25) *0(2o) w*ia w'"    can9ecl optimum solution ?

20

Management would


5.    Maximize Z = 30x1 + 20x2 + 25x3 subject to 3x1 + 2x2+ x3 < 120 (supply of Resource I)

5x1 + 3x2 + 2x3 <100 (supply of Resource 2)

Further it was possible to acquire more units of Resources 1 and 2 therefore prefer to buy excess units of Resource 2.

The goods were set as to minimize

(a)    deviation from a target profit of Rs. 2500

(b)    additional units of Resource 2 and

(c)    additional units of Resource 1.

Formulate the problem as a Goal Programming problem and solve it.

6.    (a) Find the maximum flow (units) of an item that can be transported through a network with 10

the paths listed below from source 1 to sink 5.

The paths and their capacities in units (x) are listed below :

Paths

1-2 '

1-3

2-4

2-5

3-4

3-5 2-3

X

9

12

4

11

6

10 4

Indicate the paths fully utilizing their capacities available.

(b) The following table gives activities, durations, in days and manpower requirements for a certain 10 project :

Activity

1-2

1-3

2-4

3-4

4-5

Duration

3

2

1

2

2

Manpower

4

3

2

5

4

Level out the resources without, increasing the project duration.

7. (a) The following table gives optimistic (a) most likely (m), and passimistic (c) durations, in days, 10 for activities of a certain project:

Activity

1-2

1-3

1-4

2-3

2-5

3-4

4-5

a

1

3

2

2

3

1

1

m

3

4

5

6

4

3

2

b

5

5

8

10

5

5

3

(i)    Find the mean and variance of each activity duration.

(ii)    What is the probability that the project will be completed in 5 days more than the expected duration of the project.

(b) The table below gives estimates of Normal Durations (ND), Crash Durations (CD), Normal Cost (NC) and Crash Cost (CC) for each of the project activities.

Activity

1-2

1-3

2-3

3-4

4-5

ND, days

4

5

3

4

6

CD, days

2

3

2

1

2

NC, Rs. 100

50

150

80

110

200

CC, Rs. 100

100

170

110

260

275

Indirect Cost is Rs. 60 per day.

Determine :

(i)    the minimum cost project duration

(ii)    the minimum project duration and the corresponding cost.

8. (a) For the following project, determine EST, LFT, EFT, LST, Critical path and its duration :

Activity

1-2

1-3

2-5

3-4

4-5

Duration (days)

3

2

5

6

4

10


Explain the following terms with illustration :

10


(b)


(i)    Total Float

(ii)    Gomery's Cutting Plane algorithm

(iii)    Aternative optimum, No feasible solution, unbounded solution and degeneracy in LPP.

BB-8594 [ Total Marks : 100

Con. 2175(a)-08.


( 3 Hours )


N.B. : (1)    Answer any five questions.

(2)    Figures to the right indicate full marks.

(3)    Use of Statistical Tables and Non-Programmable calculator is permitted.

(4)    Answers must be brief and to the point

(5)    Intermadiate explanations and calculations must be given.

(6)    Assumptions, wherever necessary, must be clearly stated.

10


16x2 + 25x3


X3 >


10


Minimize z = 2x2 +

xi + 2x1 +

xi


1. (a) Solve the following LPP :

Maximize z = 30xt subject to 8x1 + 4x2 + 5x3 < 1000 5x1 + 3x2 + 3x3 < 650 3x1 + 2x2 + 3x3 420, (b) Write down the Dual of the following LPP

5*,

subject to x1 + x2 > 2,

+


6x3


2 A farmer has 300 acres of land for cultivating two crops P1 and P2. The cost of cultivating P1 is Rs. 500 per acre, whereas that of P2 is Rs. 700 per acre. Budger fir cultivation available is Rs. 80,000.

Each acre of P1 requires 20 hours of labour and for P2 25 hours of labour per acre. Maximum labour hours available are 4000 hours.

The farmer wants to cultivate at least 80 acres of Pr He wants to make a profit of Rs. 200 of P1 and Rs. 300 of B. He wants to maximize the total profit.

Formulate this problem as a LPP and using Simplex method, find the optimum solution.

3. (a) State the advantages of Revised Simplex Method over Standard Simplex Method, (b) Solve the following LPP using Revised Simplex Method :

10

10


Maximize Z = 3x1 + 5x2 + 8x3

subject to


5x1 + 3x2 + 4x3 < 20 2x1 + 4x3 + 5x3 < 30

x3> 0

x15 x2,


4. (a) Solve the following LPP by Dual Simplex Method : Minimize 2 subject to

10


Minimize Z = 3x1 + 3x2 + x3


2x1 + x2 + x3 > 6 x, + x2 + 2x3 <8, xr x2, X3 > 0 (b) For the following LPP

10


Minimize Z = 190x1 + 140x2 + 200x3 subject to 2x1 + x2 + x370

xt + x2 + 2x3 80, xr x2, x30 Write down the Dual Problem and solve it. Hence find the optimum solution for the above given problem.

5. Find the optimum solution for the following LPP :

Maximize Z = 2x1 + 3x2 subject to 3x1 + x2 < 22, x 3x2 < 26 x,, x2 > 0

Find the effect on the optimum solution if :

(i)    C1 changes from 2 to 4

(ii)    b2 changes from 24 to 20

(iii)    coefficients of x1 in the constraints change from j to

(iv)    a new constraint 2x1 + 2x2 < 25 is added.

6. (a) The following table indicates duration, in days, and number of workers required for each activity 10 of the project :

Activity

1-2 1-3 2-4 3-5 4-5

Duration No. of Workers

2 3 12 3 4 2 3 4 2

Level out the manpower without increasing the project duration, (b) Consider a street network as shown below :

Numbers on the arcs indicate traffic flow capacities. The problem is to place one-way signals on the streets, not already oriented, so as to maximize the trafic flow from point s to point n.

7. (a) The following table shows for a certain project, Normal Duration (ND), and Crash Duration 10 (CD), in days, Normal Cost (NC) and Crash Cost (CC), in Rs. for activities of a certain project.

Activity

1-2

1-3

2-4

2-5

3-4

4-5

ND

5

3

4

12

7

5

CD

4

2

3

7

3

3

NC

40

60

15

40

50

25

CC

90

170

35

190

90

50

Indirect Cost is Rs. 30 per day.

Determine :

(i)    Minimum cost duration of the project.

(ii)    Minimum Duration cost for the entire project.

(b) Optimistic (a), most likely (m) and pessimestic (b) durations for a certain project are given 10 below :

Activity

1-2

1-3

2-4

3-4

4-5

a

3

6

4

9

5

m

4

9

7

12

8

b

5

12

10

15

11

(i)    Determine the expected duration and variance for each activity.

(ii)    What is the probability that the project will be completed in more them 4 days after its expected duration ?

8. (a) Consider the following pay-off matrix, with Player A as the maximising player :    10

B

Bi

b2

b3

A,

3

5

8

A,

-3

3

8

A3

4

3

6

Obtain the optimum solution for the above game problem.

(b) For a washing powder manufacturing factory, frequency distribution of contribution (x) 10 (= sales price - variable cost) per unit, annual demand (y) and requirement of investment (z) hence found as follows :

X

3 5 7

9

Prob.

'sf

CO

2

y

20

25

30 35

Prob.

1

2

6 -1

z

175

200

300

Prob.

3

5

2


Using Mont Carlo Simulation of 5 runs, estimate the percentage of return on investment. Use the following random numbers :

3025 1348 0752 3148 1234 5897 6325 1485 2008 3529 7784 3948 2145 6974

( 3 Hours )    [ Total Marks : 100

4

N.B. : (1) Answer any five questions.

(2)    Figures to the right indicate full marks.

(3)    Use of Statistical Tables and Non-Programmable calculator is permitted.

(4)    Answers must be brief and to the points.

(5)    intermadiate explanations and calculations must be given.

(6)    Assumptions, wherever, necessary, must be clearly stated.

1.    (a) Solve the following LPP :    10

Maximize Z = 3x1 + 5x2+ x3 subject to 2x1 + 4x2 + 3x3 < 40 x1 + x2 < 10

2x2 + x3 < 12, xr x2, x3 > 0

(b) Write down the dual problem for the following LPP :    10

Maximize Z = -5x1 x2 - 2x3 subject to 2x1 + 3x2 + x3> 10 x1 - 2x2 + 4x3 = 20 x1f x2 > 0 and x3 unrestricted.

vi


2.    A manufacturer produces 3 products A, B and C by using 2 types of machines Lathes (M and 20 Milling (M2). The necessary information is given in the following table :

Machine

Time, minute, per unit

Time available

A

B

c

per day in min.

M,

7

10

4

1000

m2

3

40

1

600

Profit, Rs.

per unit

45

100

30

(a)    Formulate the problem as an LPP and obtain the optimum solution.

(b)    Find the effect of changing C1 from Rs. 45 to Rs. 30 and C2 from Rs. 100 to Rs, 40.

(c)    Find the effect of changing the total time per day available on M1 and M2 to 800 and 500 minutes respectively.

(d)    A new product D requires 15 minutes on M1 and 10 minutes on M2 per unit. Will the product D will be produced if its profit, per unit, is Rs. 50 ?

(e)    Each product requires 2, 5 and 3 minutes per unit of time on a third machine, M3 find the new optimum solution, if available time, per day, on M3 is 800 minutes.

Maximize Z = 40x1 + 45x2

5.


2x1 + 5x2 + x3 < 100 (Availability of Steel)

subject to


3x1 + 3x2 + 2x3 < 120 (Availability of Rubber)

x x2, x3 > 0

Further it was possible to acquire more steel and rubber at the same original cost. But the location of steel supplier was closer. Management therefore, would prefer to buy excess of steel before buying excess rubber. The goals were set as to minimize :

(a)    deviation from a target profit of Rs. 2250

(b)    additional rubber purchase and

(c)    additional steel purchase.

Formulate the problem as a Goal Programming Problem and find the optimum solution.

6. (a) Solve the following LPP by Dual Simplex Method : Minimize 2 subject to

10


Minimize Z = 4x1 + 3x2 - x3


x1 + 3x2 - 2x3 > 20

-X, + 2*2


x3 > 0.


4x


10


(b)


For the following network, determine the

(i)    Shortest route from A to B and

(ii)    Critical Path

where A and B are source and sink nodes respectively.


10


3 >25, x,,


7. (a) For the following net-work

Activity

T

T"

00

I

T

CM

I

2-4 2-5

3-4 4-5

Duration (days)

3 2 6

5 7

2 4

10


determine the critical path, project duration and Total Float for each activity.

(b) The following table gives activities, their duration and manpower requirements for a certain project.

Activity

1-2 1-3 2-4

3-4

3-5

4-5

Duration (days)

3 2 6

7

5

4

No. of men

2 3 1

3

2

3

Level out the man power without increasing the project duration.

8. (a) A maintenance project consists of the jobs shown below. Normal Duration (ND), Crash 10 Duration (CD) in days, Normal-Cost (NC), Crash Cost (CC) in Rupees, for each job are also given below :

Activity

ND

CD

. NC

CC

1-2

5

2

100

250

1-3

2

1

50

80

2-4

5

3

150

190

3-4

3

1

80

120

4-5

2

1

60

70

Determine :

(i)    the project duration when the total cost is minimum, and

(ii)    the total project cost when the project duration is minimum.

(b) Duration of activities are uncertain. The following table gives optimistic, most likely and 10 pessimistic duration of each activity, in days :

Activity

1-2

1-3

2-3

2-4

3-5 4-5

Optimistic duration

5

15

16

8

7 3

Most likely duration

9

20

21

12

10 6

Pessimistic duration

13

25

26

16

13 9

What is the probability that the project will be completed in 4 days later than the expected project duration ?







Attachment:

( 0 Votes )

Add comment


Security code
Refresh

Earning:   Approval pending.
You are here: PAPER University of Mumbai 2008 Post Graduate Diploma SYPGDORM Part - II - Advance Operation Reserch I - Question Paper