B.B.A.(Sixth Semester) Examination, 2010
Specialization-FINANCE
Subject-Project Management
Time:Three Hours
Maximum Marks: 70

Note: ans all ques.. All ques. carry equal marks.

1. What do you mean by Project Management? define its utility and different elements.
or
elaborate the key elements of the project? How are they monitored during the project implementation stage?

2. discuss in detail the project planning activity and tools and techniques available for project planning.
or
define the care that planners must take in using a SWOT analysis for taking strategic decisions.

3. discuss the concept of network analysis. discuss the ruls for drawing a network and define it advantages.
or
Differentiate ranging from PERT and CPM. define its assumptions and benefits.

4. elaborate the various kinds of factors which affect the process of project appraisal?
or
What factors would you take into account while preparing a project? discuss the need of project formulation to make project effective.

5. explain the nature and format of a project report. Also discuss its scope and significance.
or
Differentiate ranging from management info system and project management info system. Evaluate the salient points in-valued in project related M.I.S.