Con/5096-07.    (REVISED COURSE)    CP-7335

( 3 Hours )    [Total Marks : 100

N.B. : (1)    Question No. 1 is compulsory.

(2)    Attempt any four questions out of remaining six questions.

(3)    All questions carry equal marks.

(4)    Assume suitable data if necessary.

1.    (a) Outline the steps in IGPS and explain what do you understand by IGPS 10

(Inter-group-problem-solving).

(b) Explain briefly the contents of project-master plan with examples.    10

2.    (a) What are the four types of project management roles ? Describe the 8

responsibilities and authority of managers in each role.

(b) Consider a XYZ company under take a project to computerized working of 12 ABC City Bank, then -

(i)    Develop W.B.S. for the same project

(ii)    Develop responsibility matrix.

3.    (a) Differentiate between CPM and PERT. Describe how GERT overcomes the 10

iimitations of PERT/CPM.

(b)    Describe the difference between open and closed systems, and between human 5 made and natural system.

(c)    Explain the difference between a statement of works and a contract statement 5 of work and work requisition or work order.

4.    (a) Distinguish between a interface event and milestone event. What are some 5

examples of each ? When is an interface event also a milestone event.

(b)    Explain how Gantt-chart can be used for planning and controlling small 10 projects ? What are the limitations of Gantt-chart.

(c)    Explain the difference between -    5

(i)    Total slack and free slack

(ii)    AON and AOA diagrams.

5.    (a) State and explain different types of project environment. *    10 (b) Describe the process of conducting system analysis. 10

6.    (a) Explain the system development cycle in detail.    '    10 (b) Describe cause-and-effect diagram. Pick a problem of your own choice and 10

use a cause-and-effect diagram for illustration.

7.    Write short notes on any two :    20

(a)    W. B. S.

(b)    Six Sigma

(c)    PMIS.