M.B.A-M.B.A 4th Sem COMPUTER MANAGEMENT SPECIALIZATION - V 405 - C : Software Project Management & Information Technology Management(University of Pune, Pune-2013)

Monday, 29 September 2014 12:02Nitha

   [4375] - 405 - C 

                                   M.B.A. (Semester - IV)

                                                 [Total No. of Pages : 3

 

COMPUTER MANAGEMENT SPECIALIZATION - V

405 - C : Software Project Management & Information Technology

Management

(2008 Pattern)

Time : 3 Hours]                                                                                                     [Max. Marks : 70

Instructions to the candidates:

1) Question No. 1 and 7 are compulsory.

2) Solve any four from remaining.

Q1) a) What is FPA? How FPA is used to determine cost of a project?       [5]

       b) Given the following details. Draw PERT network and state the critical

set activities in the network :                                                                   [10]


Activity        Optimistic                Most likely                 Pessimistic

                    Time (weeks)         Time (weeks)            Time (weeks)

1-2                    6                                           7                                               8

1-3                    4                                           5                                              12

1-4                    2                                           10                                            12

2-5                    3                                            7                                              11

3-7                    6                                            9                                              18

3-6                   10                                          20                                            48

4-6                    3                                             3                                               9

5-8                    3                                             3                                               9

6-9                    8                                           18                                              40

7-8                    2                                            6                                               10

8-9                   2                                             5                                               14


Q2) State the benefits of Components - based Software Development.      [10]

Q3) Draw the diagram of Project Development life - cycle and explain each step

in Brief.                                                                                                                      [10]

P.T.O.

Q4) Explain the process of Acquiring ISO - 9000 Software Certificate.    [10]

Q5) Explain Different Software risks and how to message them?                [10]

Q6) What is IT - HRM? Your answer should include selection and training

procedure of employees.        [10]

 

 

Q7) Write short notes : (any three) [15] 

a) Standards and Procedure in Software Quality Assurance.

b) Test Plan.

c) Work Breakdown structure.

d) System Walkthrough.