M.B.A-M.B.A 4th Sem COMPUTER MANAGEMENT SPECIALIZATION - V 405 - C : Software Project Management & Information Technology Management(University of Pune, Pune-2013)
[4375] - 405 - C
M.B.A. (Semester - IV)
[Total No. of Pages : 3
COMPUTER MANAGEMENT SPECIALIZATION - V
405 - C : Software Project Management & Information Technology
Management
(2008 Pattern)
Time : 3 Hours] [Max. Marks : 70
Instructions to the candidates:
1) Question No. 1 and 7 are compulsory.
2) Solve any four from remaining.
Q1) a) What is FPA? How FPA is used to determine cost of a project? [5]
b) Given the following details. Draw PERT network and state the critical
set activities in the network : [10]
Activity Optimistic Most likely Pessimistic
Time (weeks) Time (weeks) Time (weeks)
1-2 6 7 8
1-3 4 5 12
1-4 2 10 12
2-5 3 7 11
3-7 6 9 18
3-6 10 20 48
4-6 3 3 9
5-8 3 3 9
6-9 8 18 40
7-8 2 6 10
8-9 2 5 14
Q2) State the benefits of Components - based Software Development. [10]
Q3) Draw the diagram of Project Development life - cycle and explain each step
in Brief. [10]
P.T.O.
Q4) Explain the process of Acquiring ISO - 9000 Software Certificate. [10]
Q5) Explain Different Software risks and how to message them? [10]
Q6) What is IT - HRM? Your answer should include selection and training
procedure of employees. [10]
Q7) Write short notes : (any three) [15]
a) Standards and Procedure in Software Quality Assurance.
b) Test Plan.
c) Work Breakdown structure.
d) System Walkthrough.
Earning: ₹ 7.80/- |