B.Arch-B.Arch Architecture 5th Sem Project Management-521903(Sathyabama University, Chennai, Tamil Nadu-2010)

Sunday, 16 February 2014 03:24Nitha

SATHYABAMA UNIVERSITY

(Established under section 3 of UGC Act,1956)

Course & Branch :B.Arch - ARCH/MG-ARCH

Title of the Paper :Project Management                        Max. Marks :80

Sub. Code :521903                                                 Time : 3 Hours

Date :03/03/2010                                                    Session :AN

 

                                       PART - A                    (8 x 4 = 32)

                        Answer ALL the Questions

1.     What do you mean by a project? 

2.     What is a milestone chart?

3.     Draw a sketch to demonstrate event and activity and briefly explain the difference.

4.     What is work break down schedule?

5.     What is the probability of completing a project in 28 days if the expected completion of the project is 31 days and the Standard deviation of the project is 2?

6.     Define ‘time cost trade off curve’

7.     What do you mean by Crashing?

8.     What do you understand by resource allocation?

PART – B                        (4 x 12 = 48)

Answer All the Questions

9.     The activity break down for a certain project is as under

Activity No

Duration

1

1

2

2

3

4

4

3

5

1

6

2

7

4

v    Activity 2 and activity 3 can be done concurrently and both
    must follow activity 1.

v    Activity 2 must precede activity 4.

v    Activity 5 cannot begin until both activities 2 and 3 are 
    completed.

v    Activity 6 can be started only after activities 4 and 5 are
    complete.

v    Activity 7 is the last activity that can be started only after
    completion of activity 5.

Prepare the bar chart for the project.

(or)

10.   A typical small house construction project consists of the following operations along with the time set for its completion.     

Activity

Time in days

1     

3

2     

5

3     

11

4     

5

5     

2

6     

3

7     

3

8     

4

9     

4

10

4

11

3

12

2

13

3

14

1

Assumptions:

v   Activity 2 can start only after activity 1 is over.

v   Activity 3 can start when half the work of activity 2 is over.

v   Activity 4 and 5 can start concurrently, but only after activity 3 is over.

v   Activity 6 and 7 can start concurrently, but only after 5 is completed.

v   Activity 8 can start only after activities 6 and 7 are complete.

v   Activity 9 can start even when half of activity 8 is over.

v   Activity 10, 11 and 12 can start only when activity 9, 8 and 11 is over respectively.

v   Activity 13 can start when activity 10 is haft over.

The project commences on Monday 21st July. Assuming five working days in a week, prepare a bar chart of the project.

(a)    Determine total time and data of completion of the project

(b)   What is the expected progress on 17th August?

11.   A project consists of eight events having predecessor relationship as under

Event

Immediate Predecessor

Event

Immediate predecessor

1

-

5

3,4

2

1

6

3,5

3

1

7

6

4

2,3

8

4,7

        Draw the network

(or)

12.   What is the early start and finish time, last start and finish times for the project given below.       

Activity

Estimated Duration

1-2

2

2-3

3

2-4

5

3-5

4

3-6

1

4-6

6

4-7

2

5-8

8

6-8

7

7-8

4

13.   A project consists of the following activities. The time estimates are given in days.

Activity

1-2

1-3

2-4

3-4

3-5

4-5

4-6

5-6

Optimistic

2

5

4

8

3

0

1

6

Most likely time

5

7

8

10

4

0

4

9

Pessimistic time

8

11

16

14

9

0

7

12

        What is the probability of completing the project 5 days earlier than expected?

(or)

14.   Determine the optimum time duration and optimum cost for a project tabulated below:

Activity

Duration (months)

Cost (Rs.)

Normal

Crash

Normal

Crash

1-2

2

1

30,000

32,000

1-3

8

6

40,000

46,000

1-4

10

5

50,000

75,000

2-5

5

3

10,000

15,000

3-5

7

6

25,000

26,000

4-6

15

10

70,000

1,00,000

5-6

6

4

15,000

23,000

                Indirect cost = Rs.10,000 per month

15.   Level the resources within a limit of 6 and prepare a resource loading chart for the following project:        

Activity

Duration (days)

Resource requirements

1-2

6

3

1-3

8

2

1-4

4

1

2-3

4

2

2-5

8

3

3-5

7

2

4-5

10

3

(or)

16.   Level the resources for the project data given below:      

Activity

Duration (days)

Crew required

1-2

6

10

1-3

4

5

1-4

3

6

2-4

3

3

3-4

9

4

3-5

6

2

4-5

6

4