Multiple option Single ans
ques. Where does the central line is located in case of p-chart?
accurate ans at p bar
Your ans at p bar

Multiple option Single ans
ques. The product layout has subsequent disadvantage
accurate ans Layout is not flexible
Your ans Layout is not flexible

Multiple option Single ans
ques. The process of changing inputs into outputs thereby adding
a few value to entity can be described as
accurate ans Operation
Your ans Production

choose The Blank
ques. Production Planning is a centralised activity which
includes functions such as ________
accurate ans Scheduling
Your ans Scheduling

choose The Blank
ques. OC curve of ideal sampling plan suggests that all lots
less than 3% defectives have the probability of acceptance of ________.
accurate ans 1
Your ans 1

Multiple option Single ans
ques. The document which incorporates details of process
planning for a job is called
accurate ans Route Sheet
Your ans Route Sheet

Multiple option Multiple ans
ques. Which of the subsequent are kinds of non-destructive
testing?
accurate ans Visual Testing , Eddy current , Magnetic flow
detectors
Your ans Visual Testing , Eddy current , Magnetic flow detectors

Multiple option Single ans
ques. What do you understand by the difference ranging from the
specification limits within which manufacturing process is expected to
produce?
accurate ans Design tolerance
Your ans Design tolerance

Multiple option Single ans
ques. Technique of Value Engineering can be effectively employed
in design of a product to
accurate ans To meet the intended function at least cost
Your ans To meet the intended function at least cost

True/False
ques. Inspection Order can be a verbal order
accurate ans actual
Your ans False

Multiple option Single ans
ques. The ratio of output to input of a production system is
commonly known as
accurate ans Productivity
Your ans Productivity

True/False
ques. The plotting of activities - critical, non-critical and
dummy activities- is strictly according to their precedence relationship.
accurate ans actual
Your ans False

choose The Blank
ques. A ________ is a different form of subcontracting.
accurate ans Hiring capacity
Your ans Hiring capacity

Multiple option Single ans
ques. A good plant layout helps in
accurate ans Reducing handling costs
Your ans Reducing handling costs

Match The subsequent
ques. accurate ans Your ans

Combined Layout Mixed Layout Mixed Layout

Fixed Position Layout Project Layout Project Layout

Product Layout Line Layout Line Layout

Process Layout Functional Layout Functional Layout


choose The Blank
ques. A set of activities to keep an equipment in the specified
condition is called as ________.
accurate ans Maintenance
Your ans Maintenance

Multiple option Single ans
ques. How to claculate the producer risk in the OC Curve?
accurate ans Probability that a good lot will be rejected by the
sampling
Your ans Probability that a good lot will be rejected by the
sampling

Multiple option Single ans
ques. How non-critical activities are shown in the time chart
during project scheduling?
accurate ans Thin lines
Your ans Thin lines

Multiple option Single ans
ques. Any premise in which persons are employed for purpose of
making any product/s is called
accurate ans Factory
Your ans Factory

True/False
ques. Fixed cost is lower in case of continuous production than
intermittent production.
accurate ans False
Your ans False

Multiple option Single ans
ques. Inadequate production capacity ultimately leads to
accurate ans Poor Customer Service
Your ans Low Productivity

True/False
ques. Floor inspection promotes tendency of machines to drift
out of limits and produce defectives.
accurate ans False
Your ans False

choose The Blank
ques. Capacity decisions have a direct influence on performance
of production system in respect of ________
accurate ans Delivery performance
Your ans Delivery performance

Multiple option Single ans
ques. Technique which can help an organization to decrease
inventory is called
accurate ans MRP
Your ans MRP

choose The Blank
ques. The ________ is the watch dog which ensures that every
element of production and activities which could affect the quality of end
product are regulated to the extent desirable.
accurate ans Quality control
Your ans Quality control

Match The subsequent
ques. accurate ans Your ans

Temperature of motor Body Body

Exhaust gas Smell Smell

Air leakage Listen Listen

Corrosion Watch Watch


Multiple option Single ans
ques. Which characteristics are verified in cent percent
sampling?
accurate ans All important characteristics
Your ans All important characteristics

Multiple option Multiple ans
ques. elaborate the benefits of inspection and quality control?
accurate ans provide economy in production through reduction of
defective work , Adequate maintenance of quality , Ensures parts are
within specified limits of accuracy
Your ans Adequate maintenance of quality , Ensures parts are
within specified limits of accuracy , provide economy in production through
reduction of defective work

Multiple option Single ans
ques. In mass/batch production organizations where goods are
produced for stocking, Work Order is raised on the basis of
accurate ans Sales Programme
Your ans Sales Programme

True/False
ques. While making X bar-R-chart, values of X bar and R are
recoded samplewise either on the extreme right of the individual
measurements on the data sheet or in a separate sheet.
accurate ans actual
Your ans False

Multiple option Single ans
ques. What is the meaning of surplus material in situation with
stores problem order?
accurate ans Materials issued are not fully consumed
Your ans Materials issued are not fully consumed

True/False
ques. Cent percent inspection is often more practical and
economical than sampling inspection.
accurate ans False
Your ans False

Multiple option Multiple ans
ques. elaborate the benefits of reconditioning?
accurate ans Eliminates issues and frequent breakdowns ,
Increases life of an equipment , It helps to plan requirement of replacement
spares
Your ans Eliminates issues and frequent breakdowns , Increases
life of an equipment , It helps to plan requirement of replacement
spares

choose The Blank
ques. Work study is also called ________ study
accurate ans Time and Motion
Your ans Time and Motion

True/False
ques. In case of X bar, if the process is not under control
indicated by a few points falling outside the control limits, such points
outside the control limits are eliminated and new trial control limits
for the remaining points are calculated.
accurate ans actual
Your ans False

choose The Blank
ques. The easiest way to bring the delayed job within the
promised delivery time by using extra shift or weekly holiday is ________.
accurate ans Overtime working
Your ans Overtime working

True/False
ques. A sampling plan which perfectly discriminates will have
vertical OC curve.
accurate ans actual
Your ans actual

Multiple option Single ans
ques. Which of the subsequent is the most popular technique for
Project Production?
accurate ans PERT & CPM
Your ans PERT & CPM

Multiple option Multiple ans
ques. Which of the subsequent are the most suitable cases where
we can use CPA as effective technique of scheduling?
accurate ans Overhauling of a CNC machine , Purchase and
installation of a newly imported special purpose machine , Design, production
and testing of prototype of a fighter aircraft.
Your ans Overhauling of a CNC machine , Purchase and
installation of a newly imported special purpose machine , Design, production and
testing of prototype of a fighter aircraft.

True/False
ques. Sample sizes for the construction of p-chart are typicaly
larger that for Xbar-R-charts.
accurate ans actual
Your ans actual

choose The Blank
ques. The ________ advocates maintenance procedures whereby the
condition of the plant is constantly watched through systematic
inspection to unearth unhealthy conditions and preventive
accurate ans Preventive Maintenance
Your ans Preventive Maintenance

True/False
ques. It would not affect the project completion time if
non-critical activities take little loner time than planned.
accurate ans actual
Your ans actual

Multiple option Multiple ans
ques. Which of the subsequent are the basic requirements of
quality standard?
accurate ans Deifinite , Undesrstandable , Economically viable
Your ans Deifinite , Undesrstandable , Economically viable

Multiple option Single ans
ques. What is the location of lower control limit in the X bar-R
control chart?
accurate ans three standard deviations beneath central line
Your ans three standard deviations beneath central line

Multiple option Multiple ans
ques. Which of the subsequent is not the characteristic of
Project Production?
accurate ans Continuous flow of material , Highly mechanised
material handling , Virtually zero manufacturing cycle time
Your ans Continuous flow of material , Highly mechanised
material handling , Virtually zero manufacturing cycle time

Multiple option Multiple ans
ques. Which of the subsequent may be the objectives of project
crashing?
accurate ans To complete the project in the lowest possible time ,
To decrease project cost beneath it's normal cost , To achieve uniformity
in requirement of resources
Your ans To complete the project in the lowest possible time , To
decrease project cost beneath it's normal cost , To achieve uniformity in
requirement of resources

Multiple option Single ans
ques. What is the basic philosophy of statistical process
control?
accurate ans Prevention is better than cure
Your ans Prevention is better than cure






LIST OF ATTEMPTED ques. AND ANSWERS


Multiple option Multiple ans
ques. Which of the subsequent concepts must be understood for the achievement of quality?
accurate ans Quality of design , Quality of conformance , Purpose of product
Your ans Quality of conformance , Quality of design


Multiple option Single ans
ques. What do you mean by the graphical representation of the project which is composed as series of connected arrows and circles to define the interrelationship of the activities involved?
accurate ans Network
Your ans Network


Multiple option Multiple ans
ques. Which of the subsequent cases shows change in physical characteristic?
accurate ans Turning , Grinding , Drilling
Your ans Turning , Grinding , Drilling


Multiple option Single ans
ques. What do you mean by the verification of object against predetermined standards of quality or volume or both?
accurate ans Inspection
Your ans Quality assurance


Multiple option Single ans
ques. Any premise in which persons are employed for purpose of making any product/s is called
accurate ans Factory
Your ans Factory


choose The Blank
ques. The ________ advocates maintenance procedures whereby the condition of the plant is constantly watched through systematic inspection to unearth unhealthy conditions and preventive
accurate ans Preventive Maintenance
Your ans Preventive Maintenance


choose The Blank
ques. The ________ is the defect level for which lots are regarded as bad lots.
accurate ans Lot Tolerance Percentage Defective
Your ans Lot Tolerance Percentage Defective


Multiple option Single ans
ques. How non-critical activities are shown in the time chart during project scheduling?
accurate ans Thin lines
Your ans Thin lines


choose The Blank
ques. An ________ history card is the record of all repairs, replacements and engineering modifications carried out in the equipment during it's period of service.
accurate ans Equipment history card
Your ans Equipment history card


Multiple option Single ans
ques. Who prepares the daily production report?
accurate ans Shop Supervisor
Your ans Shop Supervisor


choose The Blank
ques. Work study is also called ________ study
accurate ans Time and Motion
Your ans Motion


True/False
ques. Every network does not necessarily have a critical path.
accurate ans False
Your ans False


choose The Blank
ques. Production Planning is a centralised activity which includes functions such as ________
accurate ans Scheduling
Your ans Scheduling


Multiple option Single ans
ques. Which method of critical path determination starts with the end event and moves backward to the begin event of the project network?
accurate ans Backward pass calculation
Your ans Backward pass calculation


True/False
ques. Scrap allowance is added to net requirement of material while ordering for material
accurate ans True
Your ans True


True/False
ques. Dust gets mixed with lubricants, forms an abrasive substance and causes pre-mature failure of machinery.
accurate ans True
Your ans True


Multiple option Single ans
ques. A good plant layout helps in
accurate ans Reducing handling costs
Your ans Reducing handling costs


True/False
ques. It would not affect the project completion time if non-critical activities take little loner time than planned.
accurate ans True
Your ans True


choose The Blank
ques. The ________ is the process of withdrawing the equipment from the production line, dismantling it unitwise, visualising defects, effecting adjustments, replacing worn-out parts and finally building it up to get desired accuracies.
accurate ans Reconditioning
Your ans Reconditioning


True/False
ques. Flow process charts do record movements as well as visual pictures.
accurate ans False
Your ans False


True/False
ques. Process Planning is concerned with decisions regarding requirement of machines and manpower for meeting customer demand
accurate ans False
Your ans False


Multiple option Single ans
ques. What is the meaning of " Product features" according to J.M.Juran?
accurate ans Quality of design
Your ans Quality of design


Multiple option Single ans
ques. Technique which can help an organization to decrease inventory is called
accurate ans MRP
Your ans MRP


Multiple option Multiple ans
ques. Which of the subsequent are examples of consumption of physical effort during recording for method study?
accurate ans Bending , Positioning , Unloading
Your ans Bending , Positioning , Drilling


True/False
ques. Objective of Work Study is to improve Productivity
accurate ans True
Your ans True


Multiple option Multiple ans
ques. Which 3 of the subsequent choices can be used to decrease the duration of activity during project crashing?
accurate ans Allocating more manpower and machines than originally planned for. , Working additional shifts or overtime. , Awarding work to vendors who charge extra but expedite deliveries.
Your ans Allocating more manpower and machines than originally planned for. , Working additional shifts or overtime. , Awarding work to vendors who charge extra but expedite deliveries.


Multiple option Single ans
ques. Which is the next stage to the inspection based quality control in the historical development of quality management.
accurate ans Quality assurance
Your ans Quality assurance


Match The subsequent
Question Correct Answer Your ans

Bottom compartment of control board Bunch of work orders organizes in a sequence in which they are to be processed. Bunch of work orders organizes in a sequence in which they are to be processed.

Control board Pictorial view of machine loading activity Pictorial view of machine loading activity

Top compartment of control board Work order of item currently being worked on the machine Work order of item currently being worked on the machine

Middle compartment of control board Work order of item to be processed next on the machine Work order of item to be processed next on the machine



choose The Blank
ques. The ________ is the maintenance work initiated on a outcome of knowledge of the condition of an item from routine or continuous checking.
accurate ans Condition monitoring
Your ans Condition monitoring


choose The Blank
ques. The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________.
accurate ans Overtime working
Your ans Overtime working


Multiple option Multiple ans
ques. Following are a few of the Principles of Management advocated by F W Taylor
accurate ans Selection of best worker for every particular task , Division of work ranging from worker and management , Training and development of the workmen
Your ans Selection of best worker for every particular task , Division of work ranging from worker and management , Training and development of the workmen


Multiple option Multiple ans
ques. How the concept of float is helpful to planners?
accurate ans To decide priorities in allocation of resources , To minimize the requirement of resources , To prevent peaks and valleys in requirement of resources
Your ans To decide priorities in allocation of resources , To minimize the requirement of resources


Multiple option Single ans
ques. The process of changing inputs into outputs thereby adding a few value to entity can be described as
accurate ans Operation
Your ans Operation


Multiple option Single ans
ques. Which type of defect can be called as minor defect?
accurate ans Which does not decrease the usability of the product for its intended use
Your ans Which does not decrease the usability of the product for its intended use


choose The Blank
ques. The ________ is specified to indicate the maximum permissible variability in the dimensions product or parts.
accurate ans Tolerance
Your ans Tolerance


True/False
ques. Sampling inspection is best suited when cost of inspection is much higher than the loss arising from the acceptance of a defective part.
accurate ans True
Your ans False


Multiple option Single ans
ques. Which element of a network represents a task which has got a definite beginning and definite end?
accurate ans Activity
Your ans Activity


Multiple option Multiple ans
ques. Following are the commonly used factors considered for valuation of layout in factor analysis method
accurate ans Flow of material , Equipment utilization , Working condition
Your ans Flow of material , Equipment utilization , Working condition


choose The Blank
ques. A good maintenance system is not a luxary but a ________.
accurate ans Necessity
Your ans Necessity


choose The Blank
ques. The ________ are the definitions of the measurable as well as nonmeasurable characteristics of the product.
accurate ans Specifications
Your ans Standards


Multiple option Multiple ans
ques. Which features should be covered by the specifications of materials while defining the qualitative requirement?
accurate ans Material composition , Dimensions , Any heat treatment if needed
Your ans Material composition , Dimensions , Any heat treatment if needed


Multiple option Single ans
ques. The ratio of output to input of a production system is commonly known as
accurate ans Productivity
Your ans Productivity


True/False
ques. F W Taylor devised a system for classifying motions into basic divisions called Therbligs
accurate ans False
Your ans False


Multiple option Single ans
ques. Which portion of the perforated route sheet should be signed by the operator or supervisor?
accurate ans Lower portion
Your ans Lower portion


True/False
ques. In case of X bar, if the process is not under control indicated by a few points falling outside the control limits, such points outside the control limits are eliminated and new trial control limits for the remaining points are calculated.
accurate ans True
Your ans True


Match The subsequent
Question Correct Answer Your ans

Scale model Layout analysis Modelling approach to layouts

Factor Analysis Method to evaluate layouts Technique for evolving and analysis of layouts

Minimization of production delays Objective of good layout Objective of good layout

Maximum visibility Principles of good layout Principles of good layout



True/False
ques. Maintenance function must be decentralised apart from a size of a manufacturing organisation for it's better functioning.
accurate ans False
Your ans True




LIST OF ATTEMPTED ques. AND ANSWERS


True/False
ques. Process Sheets for parts in batch production are not maintained as standard process sheet
accurate ans False
Your ans False


True/False
ques. Theoretical capacity equals number of normal working hours of that machine.
accurate ans True
Your ans True


Multiple option Multiple ans
ques. Which are the basic requirements of the " Quality of Design "?
accurate ans Identification of right product , Selection of improper features , Ensure that product renders satisfactory service to customer
Your ans Identification of right product , Selection of improper features , Ensure that product renders satisfactory service to customer


Match The subsequent
Question Correct Answer Your ans

change in chemical characteristic Chemical reaction Chemical reaction

Consumption of effort Posting a ledger Welding

info given Giving directions or instructions Posting a ledger

Subtraction Removal of worn-out part from a machine Removal of worn-out part from a machine



Multiple option Multiple ans
ques. Which of the subsequent aspects are essential to ensure quality of purchased items?
accurate ans Defining right quality for the job , Vendor performance valuation , Making sure that suppliers understand the requirements
Your ans Defining right quality for the job , Vendor performance valuation , Making sure that suppliers understand the requirements


choose The Blank
ques. The ________ is necessary when the job requires detailed of 1 or more of the job characteristics with the help of special equipment which is not available at the producing company.
accurate ans Inspection order
Your ans Move order


choose The Blank
ques. The term ________ emplies the foregone profit due to inability of company to produce.
accurate ans Opportunity cost
Your ans Idle wages


Multiple option Multiple ans
ques. Which of the subsequent factors play important role while selecting or rejecting a particular site from legislation and taxation point of view?
accurate ans Labour laws , Building codes , Policies regarding problem of licences
Your ans Labour laws , Policies regarding problem of licences


True/False
ques. Skill of labour force in a product kind layout is usually higher than in the process kind of layout
accurate ans False
Your ans False


Multiple option Single ans
ques. What is the base for considering activity time as single time estimate or 3 time estimate?
accurate ans Level of uncertainty
Your ans Level of uncertainty


Multiple option Single ans
ques. Product layout is employed for manufacturing subsequent products
accurate ans refrigirators
Your ans automobile components


True/False
ques. Diversified labour is adequately available in rural area as compared to urban area.
accurate ans False
Your ans False


Match The subsequent
Question Correct Answer Your ans

Fixation of inventory level Reorder level Single source of supply

Symptom of ill planned purchasing Over ordering Over ordering

Factor influencing material planning Lead time Reorder level

Net requirement of material under MRP Stock on hand Stock on hand



True/False
ques. In case of backward pass computation, the recent event time of the end event equals to the earliest event time minus duration of that activity.
accurate ans False
Your ans True


choose The Blank
ques. The ________ is the probability that a good lot will be rejected by the sampling plan.
accurate ans Producer's risk
Your ans Producer's risk


Multiple option Single ans
ques. Which of the subsequent technique makes 3 time estimates for every activity?
accurate ans Project valuation & Review Technique
Your ans Project valuation & Review Technique


True/False
ques. Suburban location provides the compromise netween rural and urban locations.
accurate ans True
Your ans True


Multiple option Single ans
ques. Which time is determined by the backward pass calculation method of determination of critical path ?
accurate ans Latest allowable time for every event
Your ans Latest allowable time for every event


Multiple option Single ans
ques. What do you understand by the measurement of work to establish allowed time for a job for the described method?
accurate ans Work measurement
Your ans Motion economy


True/False
ques. Even in a small set up wherein maintenance of a machine is looked after by a mechanic cum worker, he should report directly to the person responsible for the manufacturing operations.
accurate ans True
Your ans True


Multiple option Single ans
ques. Out of 2 basic criteria for the selection of a manufacturing method, 1 is, it must be able to meet the specifications of final product and the other is, it must be
accurate ans Cost effective method
Your ans Cost effective method


True/False
ques. Kanban system is essentially a computer based system for production scheduling and control
accurate ans False
Your ans True


Multiple option Multiple ans
ques. Which of the subsequent symbols are used in flow process chart but not used in operation process chart?
accurate ans Storage , Delay , Transport
Your ans Storage , Delay


Multiple option Single ans
ques. In case of Batch Production which type of labour is expected?
accurate ans Skilled in 1 specific Manufacturing Process
Your ans Skilled in 1 specific Manufacturing Process


Multiple option Multiple ans
ques. Which of the subsequent are the major steps of making of the X bar-R control chart?
accurate ans Collection of data , Claculation of mean,range,grand avg. and mean range , Set up control chart for avg. and compute control limits of range chart
Your ans Claculation of mean,range,grand avg. and mean range , Set up control chart for avg. and compute control limits of range chart , compute the coefficient of deviation


True/False
ques. For p-chart, p bar is the ratio of total number of units inspected to the total number of units defectives.
accurate ans False
Your ans True


Multiple option Single ans
ques. Which of the subsequent is the most popular technique for Project Production?
accurate ans PERT & CPM
Your ans Break Even Analysis


Multiple option Single ans
ques. Which type of preventive inspection detects a few maintenance related characteristics by making use of human senses, when equipment is in operation?
accurate ans Extrernal inspection
Your ans Internal inspection


Multiple option Single ans
ques. Process Engineer does not get sufficient time for designing tooling for most economic production run when
accurate ans Delivery time is less
Your ans Delivery time is less


Multiple option Single ans
ques. How dummy activities are shown in the time chart during project scheduling?
accurate ans Vertical lines
Your ans Dotted lines


True/False
ques. The control chart for number of defectives is more convenient to make than control chart for fraction defectives sincethe fugure of number of defectives units can be directly taken from the inspection report.
accurate ans True
Your ans True


Multiple option Multiple ans
ques. Which are the advantages of suburban location?
accurate ans Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction
Your ans Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Availability of excellent transportation and communication facilities


Multiple option Multiple ans
ques. Which utilities are considered as infrastructural requirements?
accurate ans Disposal of waste , Power , Water
Your ans Power , Labour , Water


Multiple option Single ans
ques. What do you understand by the timeframe for the maintenance needs of the equipment?
accurate ans Maintenance inspection schedule
Your ans Maintenance inspection schedule


Multiple option Multiple ans
ques. Which of the subsequent are assignable cause?
accurate ans Large varaitions in hardness of material , Tool wear , Errors in setting
Your ans Large varaitions in hardness of material , Tool wear , Errors in setting


Multiple option Single ans
ques. Which of the subsequent policies is advisable in case of low product variety and large volumes?
accurate ans Low Skilled Labour & Special Purpose Machines
Your ans Low Skilled Labour & Special Purpose Machines


Multiple option Single ans
ques. Which phase of method study is concerned with analyzing the facts critically, generating options which form the basis for selection and development of improved methods?
accurate ans Critical exam
Your ans Critical exam


choose The Blank
ques. A ________ is a different form of subcontracting.
accurate ans Hiring capacity
Your ans Collaboration


choose The Blank
ques. The ________ must ensure that the product satisfy the functional requirements of it's usage.
accurate ans Quality of design
Your ans Quality of conformance


Multiple option Multiple ans
ques. Gross requirement of finished product is determined on the basis of subsequent
accurate ans Forecasted sales , Pending sales order , Management decision to stock
Your ans Pending sales order , Management decision to stock , Gross Market requirement


choose The Blank
ques. The ________ includes preventive maintenance activities whose needs are identified through inspection which requires stoppage of machines.
accurate ans Shutdown Maintenance
Your ans Working Maintenance


choose The Blank
ques. A set of activities to keep an equipment in the specified condition is called as ________.
accurate ans Maintenance
Your ans Maintenance


Multiple option Single ans
ques. Which type of labour force is needed in case of Jobbing Production?
accurate ans Highly Skilled
Your ans Highly Skilled


choose The Blank
ques. One detachable ticket is prepared for every ________.
accurate ans Operation
Your ans Operation


choose The Blank
ques. The ________ is the watch dog which ensures that every element of production and activities which could affect the quality of end product are regulated to the extent desirable.
accurate ans Quality control
Your ans Quality control


choose The Blank
ques. The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process avg..
accurate ans Acceptable quality level
Your ans Lot Tolerance Percentage Defective


Multiple option Multiple ans
ques. Which of the subsequent products should be produced by using mass production?
accurate ans Refrigerator , Tyre for automobile , Television Set
Your ans Refrigerator , Tyre for automobile , Television Set






LIST OF ATTEMPTED QUESTIONS AND ANSWERS
LIST OF ATTEMPTED QUESTIONS AND ANSWERS 
Multiple Choice Single Answer 
Question Where does the central line is located in case of p-chart? 
Correct Answer at p bar 
Your Answer at p bar 
Multiple Choice Single Answer 
Question The product layout has following disadvantage 
Correct Answer Layout is not flexible 
Your Answer Layout is not flexible 
Multiple Choice Single Answer 
Question The process of changing inputs into outputs thereby adding 
some value to entity can be defined as 
Correct Answer Operation 
Your Answer Production 
Select The Blank 
Question Production Planning is a centralised activity which 
includes functions such as ________ 
Correct Answer Scheduling 
Your Answer Scheduling 
Select The Blank 
Question OC curve of ideal sampling plan suggests that all lots 
less than 3% defectives have the probability of acceptance of ________. 
Correct Answer One 
Your Answer One 
Multiple Choice Single Answer 
Question The document which incorporates details of process 
planning for a job is called 
Correct Answer Route Sheet 
Your Answer Route Sheet 
Multiple Choice Multiple Answer 
Question Which of the following are types of non-destructive 
testing? 
Correct Answer Visual Testing , Eddy current , Magnetic flow 
detectors 
Your Answer Visual Testing , Eddy current , Magnetic flow detectors 
Multiple Choice Single Answer 
Question What do you understand by the difference between the 
specification limits within which manufacturing process is expected to 
produce? 
Correct Answer Design tolerance 
Your Answer Design tolerance 
Multiple Choice Single Answer 
Question Technique of Value Engineering can be effectively employed 
in design of a product to 
Correct Answer To meet the intended function at lowest cost 
Your Answer To meet the intended function at lowest cost 
True/False 
Question Inspection Order can be a verbal order 
Correct Answer True 
Your Answer False 
Multiple Choice Single Answer 
Question The ratio of output to input of a production system is 
commonly known as 
Correct Answer Productivity 
Your Answer Productivity 
True/False 
Question The plotting of activities - critical, non-critical and 
dummy activities- is strictly according to their precedence relationship. 
Correct Answer True 
Your Answer False 
Select The Blank 
Question A ________ is another form of subcontracting. 
Correct Answer Hiring capacity 
Your Answer Hiring capacity 
Multiple Choice Single Answer 
Question A good plant layout helps in 
Correct Answer Reducing handling costs 
Your Answer Reducing handling costs 
Match The Following 
Question Correct Answer Your Answer 
Combined Layout Mixed Layout Mixed Layout 
Fixed Position Layout Project Layout Project Layout 
Product Layout Line Layout Line Layout 
Process Layout Functional Layout Functional Layout 
Select The Blank 
Question A set of activities to keep an equipment in the specified 
condition is called as ________. 
Correct Answer Maintenance 
Your Answer Maintenance 
Multiple Choice Single Answer 
Question How to claculate the producer risk in the OC Curve? 
Correct Answer Probability that a good lot will be rejected by the 
sampling 
Your Answer Probability that a good lot will be rejected by the 
sampling 
Multiple Choice Single Answer 
Question How non-critical activities are shown in the time chart 
during project scheduling? 
Correct Answer Thin lines 
Your Answer Thin lines 
Multiple Choice Single Answer 
Question Any premise in which persons are employed for purpose of 
making any product/s is called 
Correct Answer Factory 
Your Answer Factory 
True/False 
Question Fixed cost is lower in case of continuous production than 
intermittent production. 
Correct Answer False 
Your Answer False 
Multiple Choice Single Answer 
Question Inadequate production capacity ultimately leads to 
Correct Answer Poor Customer Service 
Your Answer Low Productivity 
True/False 
Question Floor inspection promotes tendency of machines to drift 
out of limits and produce defectives. 
Correct Answer False 
Your Answer False 
Select The Blank 
Question Capacity decisions have a direct influence on performance 
of production system in respect of ________ 
Correct Answer Delivery performance 
Your Answer Delivery performance 
Multiple Choice Single Answer 
Question Technique which can help an organization to reduce 
inventory is called 
Correct Answer MRP 
Your Answer MRP 
Select The Blank 
Question The ________ is the watch dog which ensures that every 
element of production and activities which could affect the quality of end 
product are regulated to the extent desirable. 
Correct Answer Quality control 
Your Answer Quality control 
Match The Following 
Question Correct Answer Your Answer 
Temperature of motor Body Body 
Exhaust gas Smell Smell 
Air leakage Listen Listen 
Corrosion Watch Watch 
Multiple Choice Single Answer 
Question Which characteristics are verified in cent percent 
sampling? 
Correct Answer All important characteristics 
Your Answer All important characteristics 
Multiple Choice Multiple Answer 
Question What are the benefits of inspection and quality control? 
Correct Answer Gives economy in production through reduction of 
defective work , Adequate maintenance of quality , Ensures parts are 
within specified limits of accuracy 
Your Answer Adequate maintenance of quality , Ensures parts are 
within specified limits of accuracy , Gives economy in production through 
reduction of defective work 
Multiple Choice Single Answer 
Question In mass/batch production organizations where goods are 
produced for stocking, Work Order is raised on the basis of 
Correct Answer Sales Programme 
Your Answer Sales Programme 
True/False 
Question While making X bar-R-chart, values of X bar and R are 
recoded samplewise either on the extreme right of the individual 
measurements on the data sheet or in a separate sheet. 
Correct Answer True 
Your Answer False 
Multiple Choice Single Answer 
Question What is the meaning of surplus material in context with 
stores issue order? 
Correct Answer Materials issued are not fully consumed 
Your Answer Materials issued are not fully consumed 
True/False 
Question Cent percent inspection is often more practical and 
economical than sampling inspection. 
Correct Answer False 
Your Answer False 
Multiple Choice Multiple Answer 
Question What are the benefits of reconditioning? 
Correct Answer Eliminates problems and frequent breakdowns , 
Increases life of an equipment , It helps to plan requirement of replacement 
spares 
Your Answer Eliminates problems and frequent breakdowns , Increases 
life of an equipment , It helps to plan requirement of replacement 
spares 
Select The Blank 
Question Work study is also called ________ study 
Correct Answer Time and Motion 
Your Answer Time and Motion 
True/False 
Question In case of X bar, if the process is not under control 
indicated by some points falling outside the control limits, such points 
outside the control limits are eliminated and new trial control limits 
for the remaining points are computed. 
Correct Answer True 
Your Answer False 
Select The Blank 
Question The easiest way to bring the delayed job within the 
promised delivery time by using extra shift or weekly holiday is ________. 
Correct Answer Overtime working 
Your Answer Overtime working 
True/False 
Question A sampling plan which perfectly discriminates will have 
vertical OC curve. 
Correct Answer True 
Your Answer True 
Multiple Choice Single Answer 
Question Which of the following is the most popular technique for 
Project Production? 
Correct Answer PERT & CPM 
Your Answer PERT & CPM 
Multiple Choice Multiple Answer 
Question Which of the following are the most suitable cases where 
we can use CPA as effective technique of scheduling? 
Correct Answer Overhauling of a CNC machine , Purchase and 
installation of a newly imported special purpose machine , Design, production 
and testing of prototype of a fighter aircraft. 
Your Answer Overhauling of a CNC machine , Purchase and 
installation of a newly imported special purpose machine , Design, production and 
testing of prototype of a fighter aircraft. 
True/False 
Question Sample sizes for the construction of p-chart are typicaly 
larger that for Xbar-R-charts. 
Correct Answer True 
Your Answer True 
Select The Blank 
Question The ________ advocates maintenance procedures whereby the 
condition of the plant is constantly watched through systematic 
inspection to unearth unhealthy conditions and preventive 
Correct Answer Preventive Maintenance 
Your Answer Preventive Maintenance 
True/False 
Question It would not affect the project completion time if 
non-critical activities take little loner time than planned. 
Correct Answer True 
Your Answer True 
Multiple Choice Multiple Answer 
Question Which of the following are the basic requirements of 
quality standard? 
Correct Answer Deifinite , Undesrstandable , Economically viable 
Your Answer Deifinite , Undesrstandable , Economically viable 
Multiple Choice Single Answer 
Question What is the location of lower control limit in the X bar-R 
control chart? 
Correct Answer 3 standard deviations below central line 
Your Answer 3 standard deviations below central line 
Multiple Choice Multiple Answer 
Question Which of the following is not the characteristic of 
Project Production? 
Correct Answer Continuous flow of material , Highly mechanised 
material handling , Virtually zero manufacturing cycle time 
Your Answer Continuous flow of material , Highly mechanised 
material handling , Virtually zero manufacturing cycle time 
Multiple Choice Multiple Answer 
Question Which of the following may be the objectives of project 
crashing? 
Correct Answer To complete the project in the least possible time , 
To reduce project cost below it's normal cost , To achieve uniformity 
in requirement of resources 
Your Answer To complete the project in the least possible time , To 
reduce project cost below it's normal cost , To achieve uniformity in 
requirement of resources 
Multiple Choice Single Answer 
Question What is the basic philosophy of statistical process 
control? 
Correct Answer Prevention is better than cure 
Your Answer Prevention is better than cure 
 
 
 
 
 

 

LIST OF ATTEMPTED QUESTIONS AND ANSWERS

 

 

 

 Multiple Choice Multiple Answer

  Question  

Which of the following concepts must be understood for the achievement of quality?

  Correct Answer  

Quality of design , Quality of conformance , Purpose of product

  Your Answer  

Quality of conformance , Quality of design

 

 Multiple Choice Single Answer

  Question  

What do you mean by the graphical representation of the project which is composed as series of connected arrows and circles to describe the interrelationship of the activities involved?

  Correct Answer  

Network

  Your Answer  

Network

 

 Multiple Choice Multiple Answer

  Question  

Which of the following cases indicates change in physical characteristic?

  Correct Answer  

Turning , Grinding , Drilling

  Your Answer  

Turning , Grinding , Drilling

 

 Multiple Choice Single Answer

  Question  

What do you mean by the verification of object against predetermined standards of quality or quantity or both?

  Correct Answer  

Inspection

  Your Answer  

Quality assurance

 

 Multiple Choice Single Answer

  Question  

Any premise in which persons are employed for purpose of making any product/s is called

  Correct Answer  

Factory

  Your Answer  

Factory

 

 Select The Blank

  Question  

The ________ advocates maintenance procedures whereby the condition of the plant is constantly watched through systematic inspection to unearth unhealthy conditions and preventive

  Correct Answer  

Preventive Maintenance

  Your Answer  

Preventive Maintenance

 

 Select The Blank

  Question  

The ________ is the defect level for which lots are regarded as bad lots.

  Correct Answer  

Lot Tolerance Percentage Defective

  Your Answer  

Lot Tolerance Percentage Defective

 

 Multiple Choice Single Answer

  Question  

How non-critical activities are shown in the time chart during project scheduling?

  Correct Answer  

Thin lines

  Your Answer  

Thin lines

 

 Select The Blank

  Question  

An ________ history card is the record of all repairs, replacements and engineering changes carried out in the equipment during it's period of service.

  Correct Answer  

Equipment history card

  Your Answer  

Equipment history card

 

 Multiple Choice Single Answer

  Question  

Who prepares the daily production report?

  Correct Answer  

Shop Supervisor

  Your Answer  

Shop Supervisor

 

 Select The Blank

  Question  

Work study is also called ________ study

  Correct Answer  

Time and Motion

  Your Answer  

Motion

 

 True/False

  Question  

Every network does not necessarily have a critical path.

  Correct Answer  

False

  Your Answer  

False

 

 Select The Blank

  Question  

Production Planning is a centralised activity which includes functions such as ________

  Correct Answer  

Scheduling

  Your Answer  

Scheduling

 

 Multiple Choice Single Answer

  Question  

Which method of critical path determination begins with the end event and moves backward to the start event of the project network?

  Correct Answer  

Backward pass computation

  Your Answer  

Backward pass computation

 

 True/False

  Question  

Scrap allowance is added to net requirement of material while ordering for material

  Correct Answer  

True

  Your Answer  

True

 

 True/False

  Question  

Dust gets mixed with lubricants, forms an abrasive substance and causes pre-mature failure of machinery.

  Correct Answer  

True

  Your Answer  

True

 

 Multiple Choice Single Answer

  Question  

A good plant layout helps in

  Correct Answer  

Reducing handling costs

  Your Answer  

Reducing handling costs

 

 True/False

  Question  

It would not affect the project completion time if non-critical activities take little loner time than planned.

  Correct Answer  

True

  Your Answer  

True

 

 Select The Blank

  Question  

The ________ is the process of withdrawing the equipment from the production line, dismantling it unitwise, visualising defects, effecting adjustments, replacing worn-out parts and finally building it up to get desired accuracies.

  Correct Answer  

Reconditioning

  Your Answer  

Reconditioning

 

 True/False

  Question  

Flow process charts do record movements as well as visual pictures.

  Correct Answer  

False

  Your Answer  

False

 

 True/False

  Question  

Process Planning is concerned with decisions regarding requirement of machines and manpower for meeting customer demand

  Correct Answer  

False

  Your Answer  

False

 

 Multiple Choice Single Answer

  Question  

What is the meaning of " Product features" according to J.M.Juran?

  Correct Answer  

Quality of design

  Your Answer  

Quality of design

 

 Multiple Choice Single Answer

  Question  

Technique which can help an organization to reduce inventory is called

  Correct Answer  

MRP

  Your Answer  

MRP

 

 Multiple Choice Multiple Answer

  Question  

Which of the following are examples of consumption of physical effort during recording for method study?

  Correct Answer  

Bending , Positioning , Unloading

  Your Answer  

Bending , Positioning , Drilling

 

 True/False

  Question  

Objective of Work Study is to improve Productivity

  Correct Answer  

True

  Your Answer  

True

 

 Multiple Choice Multiple Answer

  Question  

Which three of the following options can be used to reduce the duration of activity during project crashing?

  Correct Answer  

Allocating more manpower and machines than originally planned for. , Working additional shifts or overtime. , Awarding work to vendors who charge extra but expedite deliveries.

  Your Answer  

Allocating more manpower and machines than originally planned for. , Working additional shifts or overtime. , Awarding work to vendors who charge extra but expedite deliveries.

 

 Multiple Choice Single Answer

  Question  

Which is the next stage to the inspection based quality control in the historical development of quality management.

  Correct Answer  

Quality assurance

  Your Answer  

Quality assurance

 

 Match The Following

Question

Correct Answer

Your Answer

Bottom compartment of control board

Bunch of work orders arranged in a sequence in which they are to be processed.

Bunch of work orders arranged in a sequence in which they are to be processed.

Control board

Pictorial view of machine loading activity

Pictorial view of machine loading activity

Top compartment of control board

Work order of item currently being worked on the machine

Work order of item currently being worked on the machine

Middle compartment of control board

Work order of item to be processed next on the machine

Work order of item to be processed next on the machine

 

 Select The Blank

  Question  

The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking.

  Correct Answer  

Condition monitoring

  Your Answer  

Condition monitoring

 

 Select The Blank

  Question  

The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________.

  Correct Answer  

Overtime working

  Your Answer  

Overtime working

 

 Multiple Choice Multiple Answer

  Question  

Following are some of the Principles of Management advocated by F W Taylor

  Correct Answer  

Selection of best worker for each particular task , Division of work between worker and management , Training and development of the workmen

  Your Answer  

Selection of best worker for each particular task , Division of work between worker and management , Training and development of the workmen

 

 Multiple Choice Multiple Answer

  Question  

How the concept of float is helpful to planners?

  Correct Answer  

To decide priorities in allocation of resources , To minimize the requirement of resources , To prevent peaks and valleys in requirement of resources

  Your Answer  

To decide priorities in allocation of resources , To minimize the requirement of resources

 

 Multiple Choice Single Answer

  Question  

The process of changing inputs into outputs thereby adding some value to entity can be defined as

  Correct Answer  

Operation

  Your Answer  

Operation

 

 Multiple Choice Single Answer

  Question  

Which kind of defect can be called as minor defect?

  Correct Answer  

Which does not reduce the usability of the product for its intended use

  Your Answer  

Which does not reduce the usability of the product for its intended use

 

 Select The Blank

  Question  

The ________ is specified to indicate the maximum permissible variability in the dimensions product or parts.

  Correct Answer  

Tolerance

  Your Answer  

Tolerance

 

 True/False

  Question  

Sampling inspection is best suited when cost of inspection is much higher than the loss arising from the acceptance of a defective part.

  Correct Answer  

True

  Your Answer  

False

 

 Multiple Choice Single Answer

  Question  

Which element of a network represents a task which has got a definite beginning and definite end?

  Correct Answer  

Activity

  Your Answer  

Activity

 

 Multiple Choice Multiple Answer

  Question  

Following are the commonly used factors considered for evaluation of layout in factor analysis method

  Correct Answer  

Flow of material , Equipment utilization , Working condition

  Your Answer  

Flow of material , Equipment utilization , Working condition

 

 Select The Blank

  Question  

A good maintenance system is not a luxary but a ________.

  Correct Answer  

Necessity

  Your Answer  

Necessity

 

 Select The Blank

  Question  

The ________ are the definitions of the measurable as well as nonmeasurable characteristics of the product.

  Correct Answer  

Specifications

  Your Answer  

Standards

 

 Multiple Choice Multiple Answer

  Question  

Which features should be covered by the specifications of materials while defining the qualitative requirement?

  Correct Answer  

Material composition , Dimensions , Any heat treatment if required

  Your Answer  

Material composition , Dimensions , Any heat treatment if required

 

 Multiple Choice Single Answer

  Question  

The ratio of output to input of a production system is commonly known as

  Correct Answer  

Productivity

  Your Answer  

Productivity

 

 True/False

  Question  

F W Taylor devised a system for classifying motions into basic divisions called Therbligs

  Correct Answer  

False

  Your Answer  

False

 

 Multiple Choice Single Answer

  Question  

Which portion of the perforated route sheet should be signed by the operator or supervisor?

  Correct Answer  

Lower portion

  Your Answer  

Lower portion

 

 True/False

  Question  

In case of X bar, if the process is not under control indicated by some points falling outside the control limits, such points outside the control limits are eliminated and new trial control limits for the remaining points are computed.

  Correct Answer  

True

  Your Answer  

True

 

 Match The Following

Question

Correct Answer

Your Answer

Scale model

Layout analysis

Modelling approach to layouts

Factor Analysis

Method to evaluate layouts

Technique for evolving and analysis of layouts

Minimization of production delays

Objective of good layout

Objective of good layout

Maximum visibility

Principles of good layout

Principles of good layout

 

 True/False

  Question  

Maintenance function must be decentralised apart from a size of a manufacturing organisation for it's better functioning.

  Correct Answer  

False

  Your Answer  

True

 

 
 

 

LIST OF ATTEMPTED QUESTIONS AND ANSWERS

 

 

 

 True/False

  Question  

Process Sheets for parts in batch production are not maintained as standard process sheet

  Correct Answer  

False

  Your Answer  

False

 

 True/False

  Question  

Theoretical capacity equals number of normal working hours of that machine.

  Correct Answer  

True

  Your Answer  

True

 

 Multiple Choice Multiple Answer

  Question  

Which are the basic requirements of the " Quality of Design "?

  Correct Answer  

Identification of right product , Selection of appropriate features , Ensure that product renders satisfactory service to customer

  Your Answer  

Identification of right product , Selection of appropriate features , Ensure that product renders satisfactory service to customer

 

 Match The Following

Question

Correct Answer

Your Answer

Change in chemical characteristic

Chemical reaction

Chemical reaction

Consumption of effort

Posting a ledger

Welding

Information given

Giving directions or instructions

Posting a ledger

Subtraction

Removal of worn-out part from a machine

Removal of worn-out part from a machine

 

 Multiple Choice Multiple Answer

  Question  

Which of the following aspects are essential to ensure quality of purchased items?

  Correct Answer  

Defining right quality for the job , Vendor performance evaluation , Making sure that suppliers understand the requirements

  Your Answer  

Defining right quality for the job , Vendor performance evaluation , Making sure that suppliers understand the requirements

 

 Select The Blank

  Question  

The ________ is necessary when the job requires detailed of one or more of the job characteristics with the help of special equipment which is not available at the producing company.

  Correct Answer  

Inspection order

  Your Answer  

Move order

 

 Select The Blank

  Question  

The term ________ emplies the foregone profit due to inability of company to produce.

  Correct Answer  

Opportunity cost

  Your Answer  

Idle wages

 

 Multiple Choice Multiple Answer

  Question  

Which of the following factors play important role while selecting or rejecting a particular site from legislation and taxation point of view?

  Correct Answer  

Labour laws , Building codes , Policies regarding issue of licences

  Your Answer  

Labour laws , Policies regarding issue of licences

 

 True/False

  Question  

Skill of labour force in a product type layout is usually higher than in the process type of layout

  Correct Answer  

False

  Your Answer  

False

 

 Multiple Choice Single Answer

  Question  

What is the base for considering activity time as single time estimate or three time estimate?

  Correct Answer  

Level of uncertainty

  Your Answer  

Level of uncertainty

 

 Multiple Choice Single Answer

  Question  

Product layout is employed for manufacturing following products

  Correct Answer  

refrigirators

  Your Answer  

automobile components

 

 True/False

  Question  

Diversified labour is adequately available in rural area as compared to urban area.

  Correct Answer  

False

  Your Answer  

False

 

 Match The Following

Question

Correct Answer

Your Answer

Fixation of inventory level

Reorder level

Single source of supply

Symptom of ill planned purchasing

Over ordering

Over ordering

Factor influencing material planning

Lead time

Reorder level

Net requirement of material under MRP

Stock on hand

Stock on hand

 

 True/False

  Question  

In case of backward pass computation, the latest event time of the end event equals to the earliest event time minus duration of that activity.

  Correct Answer  

False

  Your Answer  

True

 

 Select The Blank

  Question  

The ________ is the probability that a good lot will be rejected by the sampling plan.

  Correct Answer  

Producer's risk

  Your Answer  

Producer's risk

 

 Multiple Choice Single Answer

  Question  

Which of the following technique makes three time estimates for each activity?

  Correct Answer  

Project Evaluation & Review Technique

  Your Answer  

Project Evaluation & Review Technique

 

 True/False

  Question  

Suburban location provides the compromise netween rural and urban locations.

  Correct Answer  

True

  Your Answer  

True

 

 Multiple Choice Single Answer

  Question  

Which time is determined by the backward pass computation method of determination of critical path ?

  Correct Answer  

Latest allowable time for each event

  Your Answer  

Latest allowable time for each event

 

 Multiple Choice Single Answer

  Question  

What do you understand by the measurement of work to establish allowed time for a job for the defined method?

  Correct Answer  

Work measurement

  Your Answer  

Motion economy

 

 True/False

  Question  

Even in a small set up wherein maintenance of a machine is looked after by a mechanic cum worker, he should report directly to the person responsible for the manufacturing operations.

  Correct Answer  

True

  Your Answer  

True

 

 Multiple Choice Single Answer

  Question  

Out of two basic criteria for the selection of a manufacturing method, one is, it must be able to meet the specifications of final product and the other is, it must be

  Correct Answer  

Cost effective method

  Your Answer  

Cost effective method

 

 True/False

  Question  

Kanban system is essentially a computer based system for production scheduling and control

  Correct Answer  

False

  Your Answer  

True

 

 Multiple Choice Multiple Answer

  Question  

Which of the following symbols are used in flow process chart but not used in operation process chart?

  Correct Answer  

Storage , Delay , Transport

  Your Answer  

Storage , Delay

 

 Multiple Choice Single Answer

  Question  

In case of Batch Production which kind of labour is expected?

  Correct Answer  

Skilled in one specific Manufacturing Process

  Your Answer  

Skilled in one specific Manufacturing Process

 

 Multiple Choice Multiple Answer

  Question  

Which of the following are the major steps of making of the X bar-R control chart?

  Correct Answer  

Collection of data , Claculation of mean,range,grand average and mean range , Set up control chart for average and calculate control limits of range chart

  Your Answer  

Claculation of mean,range,grand average and mean range , Set up control chart for average and calculate control limits of range chart , Calculate the coefficient of deviation

 

 True/False

  Question  

For p-chart, p bar is the ratio of total number of units inspected to the total number of units defectives.

  Correct Answer  

False

  Your Answer  

True

 

 Multiple Choice Single Answer

  Question  

Which of the following is the most popular technique for Project Production?

  Correct Answer  

PERT & CPM

  Your Answer  

Break Even Analysis

 

 Multiple Choice Single Answer

  Question  

Which kind of preventive inspection detects some maintenance related characteristics by making use of human senses, when equipment is in operation?

  Correct Answer  

Extrernal inspection

  Your Answer  

Internal inspection

 

 Multiple Choice Single Answer

  Question  

Process Engineer does not get sufficient time for designing tooling for most economic production run when

  Correct Answer  

Delivery time is less

  Your Answer  

Delivery time is less

 

 Multiple Choice Single Answer

  Question  

How dummy activities are shown in the time chart during project scheduling?

  Correct Answer  

Vertical lines

  Your Answer  

Dotted lines

 

 True/False

  Question  

The control chart for number of defectives is more convenient to make than control chart for fraction defectives sincethe fugure of number of defectives units can be directly taken from the inspection report.

  Correct Answer  

True

  Your Answer  

True

 

 Multiple Choice Multiple Answer

  Question  

Which are the advantages of suburban location?

  Correct Answer  

Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction

  Your Answer  

Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Availability of excellent transportation and communication facilities

 

 Multiple Choice Multiple Answer

  Question  

Which utilities are considered as infrastructural requirements?

  Correct Answer  

Disposal of waste , Power , Water

  Your Answer  

Power , Labour , Water

 

 Multiple Choice Single Answer

  Question  

What do you understand by the timeframe for the maintenance needs of the equipment?

  Correct Answer  

Maintenance inspection schedule

  Your Answer  

Maintenance inspection schedule

 

 Multiple Choice Multiple Answer

  Question  

Which of the following are assignable cause?

  Correct Answer  

Large varaitions in hardness of material , Tool wear , Errors in setting

  Your Answer  

Large varaitions in hardness of material , Tool wear , Errors in setting

 

 Multiple Choice Single Answer

  Question  

Which of the following policies is advisable in case of low product variety and large volumes?

  Correct Answer  

Low Skilled Labour & Special Purpose Machines

  Your Answer  

Low Skilled Labour & Special Purpose Machines

 

 Multiple Choice Single Answer

  Question  

Which phase of method study is concerned with analyzing the facts critically, generating alternatives which form the basis for selection and development of improved methods?

  Correct Answer  

Critical examination

  Your Answer  

Critical examination

 

 Select The Blank

  Question  

A ________ is another form of subcontracting.

  Correct Answer  

Hiring capacity

  Your Answer  

Collaboration

 

 Select The Blank

  Question  

The ________ must ensure that the product satisfy the functional requirements of it's usage.

  Correct Answer  

Quality of design

  Your Answer  

Quality of conformance

 

 Multiple Choice Multiple Answer

  Question  

Gross requirement of finished product is determined on the basis of following

  Correct Answer  

Forecasted sales , Pending sales order , Management decision to stock

  Your Answer  

Pending sales order , Management decision to stock , Gross Market requirement

 

 Select The Blank

  Question  

The ________ includes preventive maintenance activities whose needs are identified through inspection which requires stoppage of machines.

  Correct Answer  

Shutdown Maintenance

  Your Answer  

Working Maintenance

 

 Select The Blank

  Question  

A set of activities to keep an equipment in the specified condition is called as ________.

  Correct Answer  

Maintenance

  Your Answer  

Maintenance

 

 Multiple Choice Single Answer

  Question  

Which kind of labour force is required in case of Jobbing Production?

  Correct Answer  

Highly Skilled

  Your Answer  

Highly Skilled

 

 Select The Blank

  Question  

One detachable ticket is prepared for each ________.

  Correct Answer  

Operation

  Your Answer  

Operation

 

 Select The Blank

  Question  

The ________ is the watch dog which ensures that every element of production and activities which could affect the quality of end product are regulated to the extent desirable.

  Correct Answer  

Quality control

  Your Answer  

Quality control

 

 Select The Blank

  Question  

The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process average.

  Correct Answer  

Acceptable quality level

  Your Answer  

Lot Tolerance Percentage Defective

 

 Multiple Choice Multiple Answer

  Question  

Which of the following products should be produced by using mass production?

  Correct Answer  

Refrigerator , Tyre for automobile , Television Set

  Your Answer  

Refrigerator , Tyre for automobile , Television Set

 

 
 


( 0 Votes )

Add comment


Security code
Refresh

Earning:   Approval pending.
You are here: PAPER Symbiosis International Education Centre 2008 M.B.A Business Administration Production & operation Mangement - Question Paper