Cochin University of Science and Techology (CUST) 2006 B.Tech Information Technology software project management - Question Paper
BTS(C) - VII -06-045 (A)
Maximum Marks: 100
ime: 3 Hours |
B.Tech. Degree VII Semester Examination,
November 2006
IT 702 SOFTWARE PROJECT MANAGEMENT
(1999 Admissions onwards)
I a) What is the aim of software engineering? Distinguish between a program and a
software product. (10) b) List the differences between the exploratory style and modem software development
practices. (10)
OR
II a) Explain the major phases in the water fall model of software development. (10) b) Describe how a software development effort is initiated and finally terminated in the
spiral model. ' (10)
III a) Explain the components of a software project management plan (SPMP) document. (10) b) Describe work break down structure of an MIS problem. (10)
OR
IV Explain different project estimation techniques. (20)
V Describe the steps involved in software project monitoring. (20)
OR
VI a) Explain the quality factors of a software product. (10) b) Describe how a software quality management system can be developed. (10)
VII What is software configuration management? Explain the necessity of SCM. (20)
OR
VIII Describe the activities of software configuration management. (20)
IX a) Discuss the components of a productivity measurement system. (10) b) Explain how a productivity improvement program can be implemented in a software
firm. (10)
OR
X a) Define motivation. What are the factors affecting motivation? (10) b) Explain theory X and Y. (10)
***
Attachment: |
Earning: Approval pending. |