Cochin University of Science and Techology (CUST) 2008 B.Tech Civil Engineering 802 QUANTITY SURVEYING AND VALUATION - Question Paper

Sunday, 26 May 2013 02:40Web



B. Tech Degree VIII Semester Examination, April 2008

BTS (C) - VIII -08- 002 -M

CE 802 QUANTITY SURVEYING AND VALUATION

(1999 - 2001 Scheme)

Maximum Marks: 100

Time : 3 Hours


(Assume suitable data if necessary)

Estimate the quantities of the following items of work for the building shown in figure I. r 20 cm

7.5 cm LC. TERRACING

' I

y~30cm



-H90 cmh*


2 cm JL O.P.C.N 30 cm G


90 cm


2.5 cm C.C. FLOORING OVER 7:5 cm C.C. 1:5:10 L


40 cm 30 cm

10cm 30 cm 25 cm

:4;8 q q ' -,60 cm4-


,X    *-10 cm

vq J*-


50 cm

SECTIONAL ELEVATION ON AB.


1110 cm R.C.C. SLAe '20cm 3.5 m


j-30cm PROJECTION WITH DRIP COURSE 20 cm

15 cm R.C.C.

LINTEL


figure


DOOR WINDOW CHOWKATS 75 x 100 mm


TREADS 25 cm RISERS 15 cm


(Turn Over)

4 *


2

(i)    Earth work in excavation for foundation

(ii)    Brick work in Iine mortar for foundation and basement

(iii)    DPC

(iv)    Earth work in filling in plinth

(v)    Cement pointing 1:3

(vi)    Painting wood works.    (40)

OR

Prepare a detailed estimate of a RCC roof slab of 3 m clear span and 6 m long from the given figure 2. RCC work including centering and shuttering and steel reinforcement in detail shall be taken separately. Also prepare bar bending schedule.    (40)

RC.C. ROOF SLAB

figure 2.

Note//) plan bent up and top bars have been shown in dotted lines.



3

Write down specification for the following items of work :

(i)    Painting doors and windows

HI. (a)

(b)

(c)

IV. . (a) (b)


(ii)    Mosaic flooring.    (10) Differentiate between brief specification and detailed specification. (4) What are the objects of specification? (6)

OR

What are the factors affecting rate of a particular item of work?    (5)

From first principles work out the quantities of materials required for the following items of work:

(i)    PCC 1:4:8 using 40 mm aggt.

(ii)    Brick work in cm 1:6

(iii)    Plastering using cm 1:4, 12 mm thick.    (3x5=15)

Explain :

V


(i) Value    (ii) Market value

(iii) Years purchase    (iv) Leasehold.    (20)

OK

State methods of valuation.

VI. (a) (b) (C)

VII.    (a) (b) (c)

VIII.    (a) (b)


What is the purpose of valuation?

A pump set with motor has been installed at a cost of Rs. 25,000/-. Assuming the life of the pump as 15 years, work out the amount of annual installment of sinking fund required to be deposited to accumulate the whole amount of 4% compound interest.    (20)

What do you understand by Gilt edge securities? State their essential characteristics. (8) What is depreciation? What are the ways of calculating it?    (7)

Explain easement.    (5)

OR

What do you understand by rent of a property? Discuss different classifications of rents as are connected with the lease of a property.    *    (10)

A building costing Rs. 50,000,00.00 has been constructed on a free hold land measuring 100 sq.m in a big city. Prevailing rate of land is Rs. 1500 per sq.m. Determine the net rent of the property, if the expenditure on an outgoing including sinking fund is Rs. 2 lakhs per annum. Work out also the gross rent of the property per month.    (10)

***