part – A

Q1. (a) What is the difference ranging from operations management and operations strategy?
(b) explain briefly the decisions area of operations strategy.
(c) Compare and contrast the qualitative and quantitative approaches of forecasting.
[4+5+5]

Q2. (a) An enterprising college learner has relived a contract to deliver 300 vegetable sandwiches per day to a cafeteria. The learner experts to assemble these sandwiches on an assemble line using the subsequent times and precedence relationships.
Tasks Description Seconds Precedence
A Spread book buns(butter) 25 -
B Put on lettuce 15 A
C Put on vegetables 13 A
D Put on cheese 15 A
E Put on tomato 12 A
F Wrap finished sandwich 10 A,B,C,D,E

(i) For a 40 seconds cycle time, balance the line assuming the lowest number of predecessors rule. How many stations are needed and what operations are assigned to each?
(ii) What is the minimum number of stations for a 40 seconds cycle time. What is the efficiency of the balanced line found in part (i) and how long will take to produce 300 sandwiches a day. [4+5]

(b) define briefly the 3 strategies of expanding capacity. elaborate the advantages and disadvantages of incremental versus one-step expansion?

Q3. (a) discuss aggregate planning? What is the managerial significance of aggregate planning?
(b) elaborate the inputs to master scheduling? elaborate the outputs?
(c) Ram Prasad, a marketing surveyor, takes an avg. of 10 minutes to complete a particular questionnaire. Prasad's performance rating (pace) is 110% and there is allowance of 15%:
(i) What is the normal time for completing this questionnaire?
(ii) What is the standard time for completing this questionnaire?
[4+5+5]

Q4. A toy manufacturer uses 48000 rubber wheels per year for its popular dump truck series. The firm makes its own wheel which it can produce at a rate 800 per day. The toy trucks are assembled uniformly over the entire year. Carrying cost is Rupees 2/- per wheel a year. Setup cots for a production run of wheel is rupees 90/-. The firm operates 240 days per year. Determine every of the following:
(i) The optimum runs size.
(ii) The minimum total annual cost for carrying and set up.
(iii) The cycle time for the optimum run size.
(iv) The run time.
[2+2+2+1]
(b) Why selective inventory control and management are needed? elaborate the different techniques of classification for this purpose?
[7]
Q5. (a) Contrast material handling methods for a process layout and a product layout.
(b) What is enterprise resource planning (ERP) and how it can improve company's business performance?
(c) provided a data set relating sales and productions.
Sales: 1250 1380 1425 1425 1450 1300 1400 1510 1575 1650
Promotions: 41 54 63 54 48 46 62 61 64 71
(i) Establish a regression relationship ranging from sales and promotions.
(ii) Forecast the level of sales with a promotion expenditure of Rs. 50/-.
[5+4+5]

Q6. Write brief notes on any four:
(i) Total quality of services
(ii) Computer Aided Manufacturing (CAM)
(iii) Just in Time(JIT)
(iv) Principle of Materials Handling
(v) Importance of maintenance in production system.
[3.5*4]

part – B
Q7. A product is produced by 4 factories A, B, C and D. The unit production costs in them are Rs. 2, Rs. 3, Rs. 1, and Rs. five respectively. Their product capacities are Factory A – 50 units, Factory B – 70 units, Factory C – 30 units, Factory D – 50units. These Factories supply product to 4 stores, demands of which are 25, 35, 105, 20 units respectively. Unit transportation cost in rupees from every factory to every store is provided below:
Stores
S1 S2 S3 S4
2 4 6 11
10 8 7 5
13 3 9 12
4 6 8 3
A
B
Factories C
D


Determine the extent of deliveries from every factory to every store so that total production and transportation costs are minimized.
[14]