B.Tech. fifth sem Main Examination-2009
Civil Engineering
Q.S. & V.
Time: three hours Max. Marks: 80
Min. passing marks: 24


1. Enumerate various kinds of estimate and discuss every. (16)
OR
Write a short note on
a) Measurement Book
b) Abstract sheet
c) Bill of volumes
d) Methods of estimating (4x4=16)

2. (a) What do you understand by Task Work. (3)
(b) describe analysis of rates. (5)
(c) Analysis the rates of subsequent item of work .(Assume suitable rates of material and labour)
1st class brick work in superstructure with 20x10x10 cm brick with
1:6 cement and sand mortar (8)
OR
a) what do you understand by current schedule of rates. (8)
b) analysis the rates of subsequent item of work. (Assume suitable rates of material & labour)for :cement 1:2:4 (8)

3. estimate the volumes of subsequent item of 2 roomed building from a provided plan and part .
1. earthwork in excavation in foundation
2. lime concrete in foundation
3. first class brick work in cement mortar 1:6 in foundation and plinth
4. 2.5 cm cc damp proof course , and
5. first class brickwork in lime mortar in superstructure
OR
decreased level of ground along the cetre line of a proposed road from chainage 10 to chainage 20 is provided beneath. the formation level at the tenth chainage is 107 and the road is in downword gradient of one in 150 to chainage 14 and then grdient modifications to one in 100 down word , formation width of roads is 10 meter and side slope of banking are 2:1 (H:V). Length of chain is 30 meter
draw longitudinal part of the road and a typical crooss part and prepare an estimate of earth work at the rate of Rs 275/- per 100 cum.
RL of formation is 107.



chainage 10 11 12 13 14 15 16 17 18 19 20
R.L. of ground 105 105.6 105.44 105.90 105.42 104.30 105 104.10 104.62 104 103.3


4. a) explain different factor affeting the cost of work (8)
b) Enumerate different services for which provision on percentage basis is to be added in detailed estimate of building. and provide their %ge also (8)
OR
Write short notes on
a) Overhead charge
b) Contingencies
c) Work charge establishment
d) Plinth area rate (4x4=16)

5. a) describe valuatin and different pupose for which evaluation is needed. (4)
b) Enumerate the methods of evaluation and discuss every method. (4)
c) write short note on
Sinking fund
Years purchase
Scrape value
Rent fixation (2x4=8)
OR
a) What do you understand by Depreciation and discuss methods of calculating depreciation.
b) In plot of land costing Rs 20,000/- a building has been newly constructed at a total cost of Rs 80,000/- including sanitary and water supply works, electrical installation etc. The building consists of 4 flats for 4 tenants.
The owner expects eight % return on the cost of construction and 5% return on cost land. compute the standard rent for every flat of the building assuming:-
1) the life of the building as 60 years and sinking fund will be created on
4% interest basis.
2) Annual repair cost at one five of the cost of construction.
3) Other outgoing including taxes at 305 of the net return on the building (8)