How To Exam?

a knowledge trading engine...


Gujarat University 2009-3rd Year B.C.A Computer Application Software Project Management - Question Paper

Sunday, 12 May 2013 07:30Web


BCA Question Paper of April 2009

Software Project Management April 2009

Total Marks 70 Duration : 3 hrs

Instructions

 

this paper contains 5Questions of 14 marks each.

Figures on the right, indicate the marks.

Give examples Wherever needed.

1

Answer the following questions.

14

(A)

Answer any one of the following.

5

1

Depict the outline of Step Wise Planning activities.

2

List the outline of Step Wise Planning activities and sub activities.

(B)

Define a Answer .

2

1

Project.

2

Stakeholder

(c)

Answer any one of the following.

2

1

What is Management?

2

Explain the mnemonic SMART.

(d)

Answer the following.

2

1

Explain any 2 different types of Programmes.

(e)

Answer the following.

2

1

Explain any 2 Cost- Benefit Evaluation Techniques.

(f)

Answer the following.

1

1

D.C.Fern has Defined Programme as..........

2

Answer the following questions.

14

(A)

Answer any one of the following.

5

1

Explain Waterfall and V-Process Model.

2

List and explain different types of Software Prototypes .State their advantages and disadvantages.

(B)

Answer any one of the following.

5

1

Explain COCOMO Model.

2

Explain Function Point Mark II method.

(c)

Answer the following.

2

1

List and explain objectives of Activity Planning .

(d)

Answer the following.

2

1

Difine Free float and Activity Span.

3

Answer the following questions.

14

(A)

Answer any one of the following.

6

1

List and explain the different approaches to identify the activities or tasks of a project .

2

list and explain different rules for constructing Precedence Network .

(B)

Answer any the following.

5

1

Draw an Activity Network Diagram using Activity on Node Network Conventions for the following table.

Activity

Estimated Duration (in Days)

Activity

Estimated Duration (in Days)

Species overall duration

34

Design module c

4

Species module A

20

Design module D

4

Species duration B

15

Code / test module A

30

Species duration C

25

Code / test module B

28

Species duration D

15

Code / test module C

15

Check specification

2

Code / test module D

25

Design module A

15

System integration

6

Design module B

6

Apply PERT technique for the above and calculate the Z value along with the activity network diagram and tabular representation of the values.

3(B)

Explain in brief.

3

1

Parkinson's Law for software estimation.

2

Brook's Law for software estimation .

3

Monte Carlo simulation .

4

Answer the following questions.

14

(A)

Answer any the any one of following.

4

1

what action should be taken to reduce the Risk ? Explain Risk Redution Leverage with example.

2

Explain Critical Chain Concept.

(B)

Explain .

3

1

Risk .

2

Risk Reduction .

3

Mitigation .

(C)

Answer any the following.

3

1

What is Resource ? List different categories of resources and write a note on scheduling resources.

(D)

Answer any the following.

2

1

State the importance of Slip Chart or Ball Chart.

(e)

Define

2

1

Cast variance.

2

Schedule Variance

(e)

Answer any the following.

2

1

List different priorities that can be applied in deciding levels of Monitoring.

4

Answer the following questions.

14

(A)

Answer any one of following.

4

1

What action should be taken to reduce the Risk? Explain Risk Reduction Leverage with explain .

2

Explain Critical Chain Concept.

(B)

Answer any the following.

3

1

Risk .

2

Risk Reduction .

3

Mitigation .

(C)

Answer any the following.

3

1

What is Resource ? List Different categories of resources and write a note on scheduling resources .

(D)

Answer any the following.

2

1

State the importance of Slip Chart or Ball Chart.

(E)

Define.

2

1

Cost Variance.

2

Schedule Variance.

(E)

Answer any the following.

2

1

List different priorities that can be applied in decing levels of monitoring

5

Answer the following questions.

14

(A)

Answer any the following.

4

1

Define Software Quality and explain any 4 major external software quality characteristics.

(B)

Answer any the following.

3

1

Draw ISO 12207 Acquisition and Supply Process.

2

What are Fixed - Price Contracts ? State their advantage .

(C )

Answer any the any one of following.

3

1

Write a note on Leadership.

1

Explain Oldman -Hackman Job Characteristics Model .

(D)

Answer any the following.

2

1

State 2 Factors Which Causes Stress.

(E)

Answer any the following.

2

1

List any 4 General principles of Inspection given by Fagan.

 