Gujarat University 2008-3rd Year B.C.A Computer Application Software Project Management - Question Paper

Sunday, 12 May 2013 07:25Web



Scat No.: Ao

TBCA-10

April-2008

Software Project Management BCA-306 (New Course)

Time : 3 Hours)    [Max. Marks : 70

I. Do as directed (any 14):    14

What is a project ?

A projcct manager has good personal relationship with skilled resources.

[Tpie / False]

(3) Draw a diagram which displays the typical product life cyclc cash flow.

-(3) The number of spirals in a spiral model is fixed. [TpjpTaf]

In DSDM active user involvement is not required. [True/l-'sej

ifif What is expert judgement? t

jtf) List objectives of activity planning.

J&T' Define: Risk.

Qpf What is a Resource in terms of software projcct ?

(tff) Define : Cost Variance.

(11) What docs the term off-the-shelf package mean ?

(J2f* What does the Directive Autocrat leadership style indicate about the leader ?

ISO 15504 is a standard for software product assessment. [Tpde/False]

jy4) List the five levels of CMM. j    c I?

What is egoless programming ?J 1    p t

\    r\ f

(16) Define: Return on Investment.    r\

iytf) List methods to identify risk. $    

P

D. [A] Attempt any two:    10

Write a short note on waterfall model.

J&) Discuss software prototyping along with its advantages & disadvantages.

(3)    (i) What are the details that should be included in the blueprint ?

(ii) Explain in brief the role of programme manager.

(4)    Explain the major steps involved in Identify Project Scope and Objectives'. TBCA-10 I i    P.T.O.




V

aj,

[B] Attempt any two :    04

a

0

&

&

&

&

/V.

&


(1) Compare information systems and embedded systems with respect to software projects.

How can you differentiate a software project from other projects ?

'4$) Explain in brief stakeholders.

.'V

&

6

&

&

&

&

&

<&


III. [A3 Using the activity durations & precedence requirements given below, find the earliest completion date of the project & identify critical path on network.    08

Activity

Duration (days)

Precedents

A

34

B

20

A

C

15

A

D

25

A

E

15

A

F

2

B,C, D, E

G

7

F

H

6

F

I

4

F

J

4

F

K

30

G

L '

28

H

M

15

r

N

25

j

0

6

knl,m,n

OK

JAf* Explain the major rules involved in constructing precedence networks. Explain the forward pass and backward pass techniques.    08

[B] Attempt any two :    06

Jft) Explain in brief organic mode, embedded mode and semi-detached mode with reference to initial COCOMO model given by Boehm.

(2) COCOMO II is a collection of three models -Justify.

Explain in brief the five major components of Albrecht function point analysis.

&

&


TBCA-IO




&

IV. [A] Attepnpt any two :    04

What is Estimating by Analogy' technique used in software effort estimation ?

What is an activity ? How arc projects and activities related to each other ?

(3)    Mention Parkionson's law and Brook's law. What do the two laws suggest ?

B] Attempt any five :    10

What do the terms Risk Acccptancc & Risk Avoidance mean ?

[


(2) What is contingency plan ? Mention major advantages. i?f How can PERT be used to evaluate the effects of uncertainty ?

What is the significance of critical path with respect to resource allocation ?

(5) Explain in brief Total Float Priority.

J&)'' What is baseline budget ?

Mention the major characteristics of a Ball Chari.

[A] Attempt any one :    05

(1)    Write a short note on Oldham-Hackman job characteristics model.

Write a short note on ISO 9126.

[Bj Attempt any three :    09

JAY Explain in brief- Expectancy theory of motivation.

(2)    Explain the three approaches used in contractor selection. j0*Which arc the stages involved in recruitment process ?

(4)    Explain Time and Materials Contract with the help of advantages and disadvantages.

What arc software quality circles ? Explain in brief.