Project Planning and Management (BA-221)

[Time: 3 Hours] [Max. Marks: 100]

 


Before answering the question, candidate should ensure that they have been supplied the correct and complete question paper. No complaint in this regard, will be entertained after examination.

 


Note: Attempt five questions in all. Attempt any two questions from Section A and any two question from Section B. Section C is compulsory.

 

SECTION A

 

Q-1. The Escorts Groups wants to analyze the net benefits associated with a current project, in terms of social cost benefit analysis by using shadow pricing. What is shadow pricing? Discuss the important issues related to the shadow pricing of inputs and outputs of a project. (20)

Q-2. Write short notes on (20)
(a) The earned value technique
(b) Cost / schedule control system criteria

Q-3. Almost all projects are dependent on the development financial institutions for long term finance. But the institutions generally require the borrowers to meet certain norms before they tend. Explain the norms briefly. (20)

SECTION B

 

Q-4. A project was begun on 1st Jan. 2005 and was expected to be completed by 31st Dec. 2005, when the following information was developed. (20)

Budgeted cost for work scheduled (BCWS) Rs.5 million
Budgeted cost for work performed (BCWP) Rs.4.5 million
Actual cost of work performed (ACWP) Rs.5.4 million
Budgeted cost for total work (BCTW) Rs.9 million
Additional cost for completion (ACC) Rs.5 million

Calculate

(a) cost variance
(b) schedule variance in cost terms
(c) cost performance index
(d) schedule performance index
(e) estimated cost performance index

Q-2. Draw a PERI network and find out critical path.

 