B. Arch. Ill (Sem. V) Examination May / June - 2010 Specification (AR-505)

Time : 2 Hours]    [Total Marks : 50

Instruction :

1    Attempt any five out of seven :    5x2=10

True or False :

(1)    Mode of measurement is part of specification.

(2)    IS standards are part of specification.

(3)    Measurement sheet is part of specification.

(4)    For first class construction one has to use third class bricks.

(5)    LEED is an organization known as leadership in energy and environment design which helps in material and construction rating.

(6)    Architectural coatings are limited to not more than 250 g/1.

(7)    The binder is the nonvolatile part of paint or coat.

2    Both questions are compulsory question :    7+8=15

(a)    Explain in detail lump sum contract, Item rate    7 contract square meter based contract.

(b)    Discuss the minimum specification guidelines in    8 outline for class II construction from foundation of D.P.C. superstructure, roofing, flooring, wall finish frames for doors and windows.

3    Attempt any four out of the five given :    4x5=20

(1)    What are the merits and demerits of lump sum contract? Discuss.

(2)    What is meant by specification writing ? What are the different styles of writing the specification ? Discuss in brief.

(3)    What is the importance of specification in material quality control and estimation, explain with examples ?

(4)    What is the importance of mode of measurement in contract document ?

(5)    What is the benefit of the term "equivalent" in contract?

4    Attempt any five out of seven :    1x5=5

Fill in the blanks :

(1)    Lump sum is an important type of _ document.

(2)    Technical _ are termed as detailed specifications

also.

(3)    Types of tenders are _, _, _,

(4)    Detailed specification comprises of specification for _, _, And _.

(5)    Earnest money deposit is usually _ percentage of

estimated cost.

(6)    Retention money is usually _ percentage of

tender amount.

(7)    For first class construction one has to use _

class of bricks.


R-6703]    2    [ 100 ]