RM-6401 B. Arch. II (Sem. IV) Examination May/June - 2010 Building Materials & Construction - IV

Time : 3 Hours]

[Total Marks : 100

Seat No.:


Instructions :

(1)_

M    CnsLLnlcj.L{l [qoicu    u? snqw <h>h41.

Fillup strictly the details of signs on your answer book.

Name of the Examination :

B. Arch. 2 (Sem. 4)

Name of the Subject:

Building Materials & Construction - 4

-Subject Code No.:

6

4

0

1

-Section No. (1,2,.....)

Student's Signature


1&2


Figures to the right indicate full marks.

(2)

(3)

(4)

Q.1.

A.

1.


All questions have to be attempted in one answer sheet only. Support your answers with neat and clean sketches wherever necessary.

Fill in the blanks    (10)

_is the installation of temporary or permanent support to an existing

foundation to provide either additional depth or an increase in bearing capacity. _is a temporary structure used to support people and material in

the construction of buildings.

_scaffolding_does not create any obstruction on the ground and it is

3.


the most effective as it always provides the optimum level for working.

_are the transverse pieces which are placed on the ledgers and

4.


which are supported on the wall at one end.

5.    The cost of formwork plays a significant role in the cost of concrete, which varies from_of the cost of concrete for ordinary structures.

6.    Rockfill cofferdam is constructed where the depth of water to be retained by the embankment is_m.

7.    When piles are used to provide anchorage against horizontal pull from sheet piling walls or other pulling forces, they are termed as_piles.

Pneumatic type of caisson is suitable for depths ranging from_m.

8.

9.

In situations where it is desired to have increased frictional resistance between the pile stem and the surrounding,_type of pile is constructed.

10. The best spacing for timber piles is.

center to center.


B. Answer in one or two line: (support with sketch if necessary)    (10)

1.    What is an end bearing pile?

2.    What is an earthen cofferdam and in which situation it is constructed.

3.    Define caisson and its purpose.

4.    Explain vibro flotation.

5.    What is form work.

Q.2

A.    Explain the need of deep foundation and criteria to select the type of foundation for the building. Elaborate the different types of deep foundation with their specific purpose and application.    (10)

B.    Attempt any ONE:    (10) What are the different types of cast in situ concrete piles? Explain the construction of Raymond pile in detail.

OR

Explain cellular cofferdam and its types.

Q.3.

A.    Explain the different stages of construction for a low rise residential building to be constructed near a river bank. Suggest an appropriate foundation system for the same with due justification.    (10)

B.    Attempt any ONE:    (10) What are the benefits of temporary excavation shoring walls.

OR

List all the methods of underpinning and explain Pit method.

Q.4.    Write short notes on: (ANY FOUR)    (20)

1.    Under reamed pile foundation

2.    Impact of soil in deciding type of site exploration technique.

3.    Composite piles

4.    Double walled cofferdam

5.    Open caisson with dredging wells

Q.5.    Write short notes on: (ANY FOUR)

1.    Differentiate between single and double flying shores

2.    Pneumatic shores

3.    Cantilever scaffolding

4.    Form Work for circular surfaces

5.    Raking or inclined shores.

RM-6401]    2    [ 100 ]







Attachment:

( 0 Votes )

Add comment


Security code
Refresh

Earning:   Approval pending.
You are here: PAPER Veer Narmad South Gujarat University 2010-4th Sem B.Arch Architecture Rm-6401 Bldg Materials & constr.- 4 - 2 ( ) - Question Paper