Roll No. ......................
Total No. of ques. : 13] [Total No. of Pages : 02
Paper ID [B0122]
(Please fill this Paper ID in OMR Sheet)
BBA (BB - 405) (S05) (O) (LE) (Sem. - 4th)

PROJECT MANAGEMENT

Time : 03 Hours Maximum Marks : 75
Instruction to Candidates:
1) Section - A is Compulsory.
2) Attempt any 9 ques. from part - B.

part - A
Q1) (15 x two = 30)
a) Project Appraisal.
b) Project Counselling.
c) BOO.
d) Market Appraisal.
e) Project Life Cycle.
f) Debt-Equity Ratio.
g) Total Float. h) PERT.
i) Margin Money.
j) Feasibility Study.
k) Profitability Index Method.
l) Mutually Exclusive Projects.
m) Project Scheduling.
n) Cash Inflows
o) Break Even Point.

part - B
Q2) describe Project. discuss the characteristics of a project.




(9 x five = 45)

Q3) explain the issues of identification, formulation, appraisal and
implementation of new projects.

Q4) What do you mean by Project Management? Also discuss the importance of project management.

Q5) Write a brief note on consideration involved in Project Appraisal.

Q6) What do you mean by tech. Appraisal? discuss the process of tech.
Appraisal.

Q7) Write a note on techniques of Market Analysis.

Q8) elaborate the sources of finance to meet short term financial requirements?

Q9) What process is followed to measure funds requirements of a project? Q10)Critically evaluate the Internal Rate of Return technique of Capital Budgeting. Q11)What do you mean by Project Report? discuss the contents of Project Reports.
Q12)What is network analysis? Also discuss the role of network analysis in project implementation.

Q13)What is CPM? Critically evaluate this technique.