Ql. Tabic below gives the data about durations and costs of various activities of a network.
Activity |
Time in weeks |
Direct costs (Rs.) | ||
Normal |
Crash |
Normal |
Crash | |
1-2 |
4 |
2 |
4000 |
12000 |
2-3 |
5 |
2 |
3000 |
7500 |
2-4 |
7 |
5 |
3600 |
6000 |
3-4 |
4 |
2 |
5000 |
10000 |
The project overhead costs are Rs.2000 per week. Find the optimum duration and the cost associated with it. Also, draw the least cost network.
Q2. Write short notes on:
a. Importance of site records.
b. Progress recording.
c. Control of resources.
Q3. What are early warning systems? Explain monthly cost-value reporting and cost value reports.