Jaypee Institute of Information Technology (JIIT) 2008 M.Tech Civil Engineering test 3 : construction planning & control - Question Paper

Tuesday, 02 April 2013 07:55Web



JAYPEE UNIVERSITY OF INFORMATION TECHNOLOGY

WAKANAGHAT TEST-3 M.Tech. (CTM) 1st Scm. 2008 Course Code: 07MI1CE103    Max.Time: I Hr. 30 Mins Course Name: Construction Planning and Control    Max.Marks: 30 Course Credit: 3

Ql. Tabic below gives the data about durations and costs of various activities of a network.

Activity

Time in weeks

Direct costs (Rs.)

Normal

Crash

Normal

Crash

1-2

4

2

4000

12000

2-3

5

2

3000

7500

2-4

7

5

3600

6000

3-4

4

2

5000

10000

The project overhead costs are Rs.2000 per week. Find the optimum duration and the cost associated with it. Also, draw the least cost network.

(20)

Q2. Write short notes on:

a.    Importance of site records.

b.    Progress recording.

c.    Control of resources.

(6)

Q3. What are early warning systems? Explain monthly cost-value reporting and cost value reports.