1. Discuss the advantages and disadvantages of Project Management. 5 marks
2. Explain the projcct lifecycle. clearly highlighting the phases. 6 marks
3. Assume that two Arms are competing for market share. The payoff matrix of describes the percentage gain for player A 3 marks
a. Determine optimal strategies for both firms
b. Is the game fair
c. What would be the market share of player A on using optimal strategy.
Fir B | |||
Firm A |
No Ptoroouon |
Mo&me Promotion |
lligk promotion |
Not*ranoom |
0 |
15 | |
SfofaraM Promotion |
i: |
t |
.4 |
FiimCm! |
20 |
IS |
6 |
4. A company uses certainty-cquivalcnt approach to adjust the projcct risk. Using a discount rate of 12% compute ihe risk adjusted NPV. 6 marks
Year |
a |
I |
2 |
3 |
1 4 |
5 : |
Cash (low |
64,000 |
18.000 |
20,000 |
21.000 |
1 22.000 |
12,000 |
C.E Coefficient |
1 |
0.95 |
0.90 |
0.85 |
0.85 |
0.70 1 |
PVIF | ||||||||||||||||||||||||||||||||||||||||||
|
Attachment: |
Earning: Approval pending. |