Uttar Pradesh Technical University (UPTU) 2007 B.Tech Project management - Question Paper
Printed Pages : 2 ME-601
(Following Paper ID and Roll No. to be filled in your Answer Book)
(SEM. VI) EXAMINATION, 2006-07 PROJECT MANAGEMENT
Time : 2 Hours] [Total Marks : 50
Note : Attempt all the questions.
1 Attempt any four parts of the followings : 3 x4=14
(a) What background informations are required for defining goals of a project ? Explain.
(b) Describe the procedure of breaking down a structure in forming an organization. Explain with example.
(c) Write short note on the followings:
(i) Letter of indent
(ii) Open tender
(iii) Performance measurement indicators
(d) List the responsibilities of a project manager. Describe coordination in detail.
(e) Explain the difference between internal and external project control.
(1) Describe the features and properties that distinguish human organization from other systems.
V-4049] 1 [Contd...
2 Attempt any two parts : 6x2=12
(a) Differentiate between Project Management Information System and Ordinary Management Information System. Discuss the basic information required for a good Project Management Information System.
(b) Name and describe the functions which are performed better with computer based project management information system.
(c) Discuss the difficulties encountered in managing a project. Explain with an actual example.
3 Attempt any two parts : 6x2=12
(a) Explain followings with one example :
(i) Total float
(ii) Independent float
(iii) Free float.
(b) Describe three time estimates used in a PERT network. Show these time estimates on the frequency distribution they follow.
(c) Describe the process of crashing a network in detail.
4 Attempt any two parts : 6x2=12
(a) Describe the five elements of Total Quality Management.
(b) What is ERP ? How is it different from MRP ? Discuss any one popular ERP Software.
(c) Explain the following terms and their use in MRP :
(i) Bill of material
(ii) Master Schedule.