Note : (i) Attempt all questions.

(ii)    In case of numerical problems assume data wherever not provided.

(iii)    Be precise in your answer.

1 Attempt any four parts of the following:    5x4=20

a)    Discuss different types of estimates in short.

b)    Write general specifications of 1st class building.

c)    Write detailed specifications of 1:4:8 cement concrete in foundation.

d)    What are different methods of estimation? Which method you adopt for octagonal bay front building ?

e)    Calculate the earthwork in excavation of foundation for a room of internal size 5m x 4 m with 300 mm thick walls, the width and depth of the foundation being 700 mm and 900 mm respectively.

f)    Enumerate general items of work and mention their units of measurement for building construction.

V-0060]    1    [Contd...

a)    What do you understand by analysis of rates. Discuss its importance.

b)    What is a work charged establishment ? Discuss its importance with respect to regular establishment.

c)    Work out analysis of rates for 1:2:4 R.C.C work in slab.

d)    Discuss the procedure followed regarding adoption of market rates and cost indices with reference to P.W.D schedule of rates.

e)    Discuss briefly the relative merits and demerits of different methods of valuation.

f)    Work out analysis of rates for 25 mm thick D.P.C

3 Attempt any two parts of the following: 10x2=20

a)    What are main advantages the network method have over the conventional methods of planning and scheduling?

b)    The network for a certain project is shown in fig.l. Determine the expected time for each of the path. Which path is critical ?

c) Explain in brief of the following :

i)    AOA diagram

ii)    Standard deviation

iii)    Most likely time estimate

iv)    Latest allowable occurrence time.

4    Attempt any two parts of the following : 10x2=20

a)    Explain the methods of time cost optimization of project network.

b)    What is need of financial management? Describe in short different types of financing.

c)    Explain the following in brief :

i)    Project monitoring

ii)    Time value of money

iii)    Depreciation

iv)    Equivalence concept.

5    Attempt any two parts of the following : 10x2=20

a)    What are the different types of engineering contracts? What are the essential documents required in a contract?

b)    Write a suitable tender notice for the construction of an office building for the value of rupees 130 lakhs.

c)    Explain the following :

i)    Earnest money

ii)    Work order

iii)    Evaluation of tender

iv)    Legal aspects of contracts.

V-0060]    3    [ 250 ]


TCE - 604

*V-0060*

Printed Pages : 3

(Following Paper ID and Roll No. to be filled in your Answer Book)

IroII No.

PAPER ID : 0060


B. Tech.

(SEM. VI) EXAMINATION, 2006-07 ESTIMATION & CONSTRUCTION MANAGEMENT

Time : 3 Hours]    [Total Marks : 100

Note : (i) Attempt all questions.

(ii)    In case of numerical problems assume data wherever not provided.

(iii)    Be precise in your answer.

1 Attempt any four parts of the following:    5x4=20

a)    Discuss different types of estimates in short.

b)    Write general specifications of 1st class building.

c)    Write detailed specifications of 1:4:8 cement concrete in foundation.

d)    What are different methods of estimation? Which method you adopt for octagonal bay front building ?

e)    Calculate the earthwork in excavation of foundation for a room of internal size 5m x 4 m with 300 mm thick walls, the width and depth of the foundation being 700 mm and 900 mm respectively.

f)    Enumerate general items of work and mention their units of measurement for building construction.

V-0060]    1    [Contd...

a)    What do you understand by analysis of rates. Discuss its importance.

b)    What is a work charged establishment ? Discuss its importance with respect to regular establishment.

c)    Work out analysis of rates for 1:2:4 R.C.C work in slab.

d)    Discuss the procedure followed regarding adoption of market rates and cost indices with reference to P.W.D schedule of rates.

e)    Discuss briefly the relative merits and demerits of different methods of valuation.

f)    Work out analysis of rates for 25 mm thick D.P.C

3 Attempt any two parts of the following: 10x2=20

a)    What are main advantages the network method have over the conventional methods of planning and scheduling?

b)    The network for a certain project is shown in fig.l. Determine the expected time for each of the path. Which path is critical ?

c) Explain in brief of the following :

i)    AOA diagram

ii)    Standard deviation

iii)    Most likely time estimate

iv)    Latest allowable occurrence time.

4    Attempt any two parts of the following : 10x2=20

a)    Explain the methods of time cost optimization of project network.

b)    What is need of financial management? Describe in short different types of financing.

c)    Explain the following in brief :

i)    Project monitoring

ii)    Time value of money

iii)    Depreciation

iv)    Equivalence concept.

5    Attempt any two parts of the following : 10x2=20

a)    What are the different types of engineering contracts? What are the essential documents required in a contract?

b)    Write a suitable tender notice for the construction of an office building for the value of rupees 130 lakhs.

c)    Explain the following :

i)    Earnest money

ii)    Work order

iii)    Evaluation of tender

iv)    Legal aspects of contracts.

V-0060]    3    [ 250 ]







Attachment:

( 0 Votes )

Add comment


Security code
Refresh

Earning:   Approval pending.
You are here: PAPER Uttar Pradesh Technical University (UPTU) 2007 B.E Civil Engineering estimatoin and construction management - Question Paper