M.C.A-M.C.A 5th Sem BM-51 : SOFTWARE PROJECT MANAGEMENT(University of Pune, Pune-2013)
M.C.A. (Management Faculty) (Semester - V) Examination, 2013
BM-51 : SOFTWARE PROJECT MANAGEMENT
(2005 Pattern)
Time : 3 Hours Max. Marks :70
Note : 1) Q. 1 and Q. 8 are compulsory.
2) Solve any five from Q. 2 to Q. 7.
1. Draw network diagram for the following project activities and find the critical
path. 10
S. No. Activities Precedence Days
1 A - 3
2 B - 4
3 C A 5
4 D A 6
5 E C 7
6 F D 8
7 G B 9
8 H E, F, G 3
2. What are the various Cost Estimation Techniques ? Explain COCOMO Model in detail.
3. What is meant by Risk Management ?
4. Discuss the role of Quality Assurance during Software Development.
5. Discuss Managing Customer Expectation.
6. Explain Software Configuration Management. 10
7. What are the characteristic of performance management in IT Team ?
8. Write a note on (any 2) :
a) User Acceptance Testing
b) Role of User in Software Project Management
c) MS-Project d) Baseline.