M.C.A. (Management Faculty) (Semester - V) Examination, 2013

BM-51 : SOFTWARE PROJECT MANAGEMENT

(2005 Pattern)

Time : 3 Hours                                                                                                              Max. Marks :70

Note : 1) Q. 1 and Q. 8 are compulsory.

2) Solve any five from Q. 2 to Q. 7.

1. Draw network diagram for the following project activities and find the critical

path.                                                                                                                                             10


S. No.                            Activities                                 Precedence                                    Days

 

  1                                A                                       -                                         3

  2                                B                                      -                                        4

  3                                C                                      A                                       5

  4                                D                                      A                                       6

  5                                E                                       C                                       7

  6                                F                                       D                                       8

  7                                G                                      B                                       9

  8                                H                                     E, F, G                                3

2. What are the various Cost Estimation Techniques ? Explain COCOMO Model in detail.

3. What is meant by Risk Management ?

4. Discuss the role of Quality Assurance during Software Development.

5. Discuss Managing Customer Expectation.


 

6. Explain Software Configuration Management.                                                                 10


7. What are the characteristic of performance management in IT Team ?

8. Write a note on (any 2) :

a) User Acceptance Testing

b) Role of User in Software Project Management

c) MS-Project d) Baseline.