Combined First and Second Semester B.Tech. Degree Examination, May 2009

(2008 Scheme)

08-106 BASIC CIVIL ENGINEERING

Max. Marks : 100

Time : 3 Hours


PARI' - A

Answer all questions.

1.    Explain ihe principles of surveying

2.    List out the errors in tape measurement

3.    Sketch a typical page in a levelling field book

4.    Mention the characteristics of contour maps.

5.    What is beaming capacity of soil ? How will it affect the selection of foundation ?

6.    What is the criteria of selection of roofing materials

7.    Differentiate between precast and prestressed concrete

8.    Explain any two systems of vertical transportation.    (8x5=40 Marks)

PART - B MODULE - 1

9. a) What is ranging ? Explain the different methods of ranging.

8


b) To measure a base line, a steel tape 30 m long standardised at 15(. with a pull

of 100 N was used. Find the correction per tape length if the temperature at the time of measurement was 20C and the pull exerted was 160 N.

E = 2.1 xlO7 N/cm\ a = 7.1 xl0r 7C, wt of I cm1 of steel = 7.86 gm.

OR

12

PT.O.


10. a) Explain the significance of Total station and GPS in surveying in the present context.

b) A series of offsets was taken from a base line to a curved boundary at intervals of 10 m in the following scqucncc

0. 2.68, 3 64. 3 70. 4 60. 3 62. 4 84. 5 74

Complete the area between the base line, the curved boundary line and the end offsets using Simpson's rule and compare the results with trapezoidal rule

MODULE - 2

(la) What are the criteria for selection of site for buildings ?

b> Draw neat sketches of a spread footing, isolated foottng. and Mat foundation

OR

12.    a) Name the different types of stone measoury with sketches, b) What is plastering ? Explain the procedure for the same

MODULE - 3

13.    a) Enumerate the IS specifications for the different tests on cement.

b) How is plain cement concrete mixture proportioned and prepared ?

OR

14 a) How is Reinforced cement concrete compared with plain cement concrete ?

b> Explain briefly the water supply and sewage disposal arrangements in a residential building.