How To Exam?

a knowledge trading engine...


Biju Patnaik University of Technology 2008-7th Sem B.Tech Power System Operation & Control - Question Paper

Thursday, 23 May 2013 11:30Web




Total number of printed pages-7    B. Tech

CPEE 5401

Seventh Semester Examination - 2008 POWER SYSTEM OPERATION AND CONTROL Full Marks - 70

Time : 3 Hours

Answer Question No. 1 which is compuSsoty and any five from the rest

_ The figures in the nght-hand margin indicate msrks.

1. Answer the following questions : 2 *10

(i) What is meant by 'compact storage scheme11 in load flow analysis ?

(j|) What is meant by terms Jacobian ?

(iii) Why a direct solution of load flow is not possible ?

P.T.O.

(iv)    Why a majority of buses in power systems are load buses ?

(v)    Differentiate between stability and loss of synchronous,

(vi)    What is transfer reactance ?

(vii)    A power system network consists of three elements 0-1, 1-2 and 2-0 of per unit impedances 0.2, 0,4, and 0.4 respectively. What is its bus impedance matrix?

(vtiij Principle of Equai-area criterion is to be applied to determine, for a given initial

load P., the maximum amount of sudden

i *

increase in load a P, to maintain transient stability of a cylindrical rotor synchro-nous motor operating from an infinite bus. Applying this criterion (in each case the area A1 - area A2), draw the correct diagram.

CPEE 5401    a    Conld.

(ix)    With 100% inductive shunt compensation the voltage profile will be flat for what percentage loading of line Briefly explain your answer

(x)    What are the effects of series capacitance compensation ?

(a)    Analytically establish the role of reactive power on receiving end voltage and voltage regulation of the bad bus. 4

(b)    What is reactive compensation and what are the benefits 7    2

(c)    Describe different types of reactive power compensation in brief    4

(a)    Give a flow chart for a load flow study on a power system having only P-Q buses using G*S method. How does the flow chart get modified to account for PV buses ?    4

(b)    Fig. 1 shows a five bus power system. Each line has an impedance of

5EE 5401    3    P.T.O.

0.05 +-j0.15pu The line shun! admittances may be neglected. The bus power and voltage specifications are given below :

Bus

ql

PS

qg

V

Bus

Specification

1

1.0

0 5

Nol

Speeded

Not i Specified

1 02<0

Slack Dus

2

0

0

2

Not

Specified

1 02

PV Bus

3

0.5

0.2

0

0

Not

Specified

PQ Bus

*** 1 A

0,5

0.2

0

0

Not

Specked

PQ Bus

5

0.5

0.2

0

0

Not

Specified

PQ Bus j

IWL

(i) Form Y

DUS

CPEE 5401

Contd.


(ii] Find Q?l    V4 and after the first

iteration using Gauss-Seidel method. Assume 0 = 0 2 pu and Q =0.6 pit,

6

(a)    Distinguish between steady state, transient and1 dynamic stability Derive power angle equation.    5

(b)    Using equal area criterion, derive an expression for critical clearing angle for a system having a generator feeding a large system through a double circuit line    5

A 50 HZ generator of reactance 0 8 pu is connected to an infinite bus through a line of

0 4 pu reactance E = 1.05 pu, V = 10 pu The inertia constant is 4 MJ.'MVA The generator is loaded to 70% of the maximum power limit Find the frequency of natural oscillations Derive the formula used    0

6. A single area consists of two generating units, rated at 400 and 800 MVA, with speed regulation of 4% and 5% on their respective ratings. The units are operating in parallel, sharing 700 MW. Unit 1 supplies 200 MW and unit 2 supplies 500 MW at 1.0 per unit (60 Hz) frequency. The load is increased by 130 MW.

10

(a)    Assume there is no frequency dependent i load, i.e., D = 0. Find the steady-state frequency deviation and the new generation on egch unit.

(b)    The load varies 0.804 percent for every

1 percent change in frequency, i.e.,

D = 0.804. Find the steady state frequency deviation and the new generation on each unit.

On a system consisting of two generating "plants the incremental costs in rupees per megawatt-hour with P1 and P2 in megawatts are

dR    dF,

= O.OOP, + 8.0 and p- = 0.012P + 9.0 dP1    1    dP2    2

The system is operating on economic dispatch with P1 = P2 = 500 MW and sP/gP 0.2. Find the penalty factor of plant 1.    10

Write short note on :    5*2

(a)    Methods of improvement of transient stability.

(b)    Economic dispatch controller.

PEE 5401    7    -C







Attachment:

( 0 Votes )

Add comment


Security code
Refresh

Earning:   Approval pending.
You are here: PAPER Biju Patnaik University of Technology 2008-7th Sem B.Tech Power System Operation & Control - Question Paper