M. C. A. (Sem. - II) Examination April/May - 2010 Paper - 204 : Computer Based Optimization Techniques

(Old & New Course)

[Total Marks : 70

Time : 3 Hours]


Instructions

(1)

""'N Seat No.:


6silq<3i Puunkiufl [qaim SuwiA u* qsq d-onql. Fillup strictly the details of signs on your answer book.

Name of the Examination :

M. C. A. - 2

Name of the Subject:

204 - COMPUTER BASED OPTIMIZATION TECHNIQUES

Student's Signature


-Subject Code No.

1 1

8

0

1 1

-Section No. (1,2,.....): NIL

(2)    The marks for each question is given in right side of each question.

(3)    All questions carry equal marks.

Answer the following questions:

1 .a. Define the following terms in relation to linear programming:    [6]

(i)    Basic feasible solution, (ii) Slack variable,

(ii)    Optimum solution, (iv) Associated cost vector.

1 .b. Solve the following linear programming problem:    [8]

Minimize z = xi - 3x2 + 2x3, subject to 3xi - x2 + 3x3 < 7,

-2xi+ 4x212,

-4xi + 3x2 + 8x3 < 10, xj>0, x2>0, x3>0.

OR

1 .b. Solve the following linear programming problem:    [8]

Maximize z = 6x1 + 8x2 + 4x3 + 3x4, subject to 2xi + 3x2 + x3 < 900,

X2 + 2x3 < 600,

3xi + 2x2 + 2x3 < 1200,

3x3+ X4= 100,

Xi>0, X2>0, X3>0,X4>0.

2.a. A manufacturer produces three models (I, II,III) of a certain product. He uses two types of raw materials (A and B) of which 4000 and 6000 units respectively are available. The raw material requirements per unit of the three models are given below:    [6]

Raw

Requirement per unit of given model

Material

I II III

A

2 3 5

B

4 2 7

The labour time for each unit of model I is twice that of model II and three time that of model III. The entire labour force of the factory can produce can produce the equivalent of 2500 units of model I. A market survey indicates that the minimum demand of the three models are 500, 500 and 375 units respectively. However, the ratios of the number of units produced must be equal to 3:2:5. Assume that the profit per unit of model I, II and III are Rs. 60, 40 and 100 respectively. Formulate the problem as linear programming problem in order to determine the number of units of each product which will maximize profit.

2.b. Obtain the optimum solution for the following transportation problem:    [8]

Warehouses

W, W9 W. W* W<    Available

F, | 4 3 1 2    6 |    40

Factory F21 5 2 3 4    5 |    30

F3| 3 5 6 3    2 |    20

F4| 2 4 4 5    3 |    10

Required 30 30 15 20 5

OR

2.b. Obtain the optimum solution for the following transportation problem:    [8]

Warehouses

1

2

3

4

5

6

Available

11

5

3

7

3

8

5 1

3

2|

5

6

12

5

7

1L]

4

From City 3 |

2

8

3

4

8

2

1 2

4|

9

6

10

5

10

9 1

8

Required

3

3

6

2

1

2

3.b. A certain equipment needs five repair jobs which have to be assigned to five machines. The estimated time (in hours) that each machine requires to complete the repair job is given in the following table:    [7]

Job

1

2

3

4

5

11

7

5

9

8

11

2|

9

12

7

11

10

3 |

8

5

4

6

9

4|

7

3

6

9

5

51

4

6

7

5

11

Assuming that each machine can be assigned to only one job, determine the minimum time assignment.

3.b. Find an optimal sequence for the following sequencing problem of 5 jobs and 4 machines when passing is not allowed of which processing time (in hours) is given below:    [7]

Jobs :

1

2

3

4

5

Machine Mi:

10

12

8

15

16

Machine M2:

3

2

4

1

5

Machine M3:

5

6

4

7

3

Machine M4:

14

7

12

8

10

Also find total elapsed time.

OR

3.a. Solve the following traveling salesman problem.    [7]

To

1

2

3

4

5

1 oc

17

16

18

14 I

1 17

OC

18

15

16 |

1 16

18

OC

19

17 |

1 18

15

19

OC

18 |

1 14

16

17

18

oc |

3.b. Find the optimal sequence for the following sequencing problem of 4 jobs and 5 machines when passing is not allowed of which processing time in (hours) is given below:

Jobs :

1

2

3

4

Machine Mi:

6

5

4

7

Machine M2:

4

5

3

2

Machine M3:

1

3

4

2

Machine M4:

2

4

5

1

Machine M5:

8

9

7

5

Also find the total elapsed time.

4.a. Define the following terms:    [4]

(i) Earliest finish time (ii) Pessimistic time

(iii) Estimated time (iv) Successor activity

4.b. The following table gives the activity times (in days) for a small project:    [10]

Activity

Optimistic

Time

Most Likely Time

Pessimistic

Time

1 - 2

1

2

9

2 - 3

1

4

7

2 - 4

2

4

12

3 - 5

2

3

4

3 - 7

6

8

15

4 - 5

4

6

8

4 - 6

3

5

7

5 - 6

5.

1

15

5 - 7

5

7

15

6 - 7

3

5

13

(i)    Construct the network.

(ii)    Compute earliest and latest times for each activity.

(iii)    Find the critical path and its duration.

(iv)    What is the probability that the project should be completed in 25 days?

OR

4.a. Define the following terms:

[4]


(i) Critical path (ii) Critical activity

(iii) Merge event (iv) Cost slope.

4.b. The following table gives the data on normal time, normal cost, crash time and crash cost for a small project.    [10]

Activity

Time fdavs)

Cost (Rs.)

Normal,

Crash

1 Normal

Crash |

1 -

2

6 !

4

| 1400

1900 |

1 -

3

8 I

5

| 2000

2800 |

2 -

3

4 |

2

| 1100

1500 |

2 -

4

3 1

2

| 800

1400 [

3 -

4

o !

0

1 o

0 |

3 -

5

6 1

3

| 900

1600 |

4 -

6

10 |

6

2500

3500 |

5 -

6

3 1

2

1 500

800 1

Indirect cost is Rs. 300 per day.

(i)    Draw the network.

(ii)    Find the critical path.

(iii)    Find the optimum project time and corresponding minimum total cost by crashing appropriate activities in proper order.

5.b. Consider a shop which produces three items. The items are produced in lots. The demand rate for each item is constant and can be assumed to be deterministic. No back logs are to be allowed. The pertinent data for the items are given below: [4]

Product :

1

2

3

Annual demand (Units/year):

11000

140000

8500

Holding cost/ unit (Rs.) :

30

30

30

Set-up Cost per lot (Rs) :

60

50

70

Determine approximately the economic order quantities when the average inventory level of these items is 1050.

5.c. A baking company sells one of its type of cake by weight. If the product is not sold on the day it is prepared, it can be sold at a loss of 15 paise per Kg. and there is an unlimited market for one day old cake. The company makes a profit of 95 paise on every Kg. of cake sold on the day it is prepared. Past daily orders form a distribution with density function:    [3]

f(x) = 0.02 - 0.0002x,    0<x<l 00.

How many Kg. of cake should the company prepare every day?

5.d. Find the optimum order quantity for a product for which the breaks are as follows:

[3]

Quantity Range    Purchasing cost

0 < Q < 400    Rs. 145.00 per unit

400 < Q < 800    Rs. 135.00 per unit

800 and above    Rs. 130.005 per unit

The monthly demand for the product is 4500 units. The monthly holding cost is 2% of the unit cost of the product and the cost of ordering is Rs. 700.00 per month.

OR

5.a. Find the optimum order quantity for a product for which the breaks are as follows:

[4]

Quantity Range    Purchasing cost

0 < Q < 250    Rs. 8.00 per unit

250 <Q< 450    Rs. 7.50 per unit

450 < Q < 650    Rs. 7.00 per unit

650 and above    Rs. 6.75 per unit

The monthly demand for the product is 900 units. The monthly holding cost is 20% of the unit cost of the product and the cost of ordering is Rs. 45.00 per month.

5.b A machine shop produces three products 1,2 and 3 in lots. The shop has a warehouse whose total floor area is 350 sq. meters. The relevant data for the three items are given below:    [4]

Product    : 1 2 3

Annual demand (Units/year): 4000 3000 8000 Holding cost/unit (Rs.) : ]5 20 10 Set-up cost per lot (Rs.) : 90 180 70 Floor area required    : 0.70 0.85 0.45

(sq. meters)

The carrying charge on each item is 20% of the average inventory valuation per annum. No stock outs are allowed. Determine the optimal lot size for each item.

5.c. The demand of an item is uniform at a rate of 30 units per month. The set-up cost is Rs. 20 each time a production run is made. The inventory carrying cost is Rs. 0.45 per item per month. If the shortage cost is Rs. 2.25 per item per month, determine how often to make a production run and of what size it should be?    [3]

5.d. The probability distribution of monthly sales of a certain item is as follows: [3]

Monthly Sales: 40 41 42 43 44 45 46 47 48 49 50 51 Probability : 0.03 0.05 0.05 0.10 0.15 0.15 0.12 0.10 0.10 0.07 0.06 0.02

The cost of carrying inventory is Rs. 1.80 per unit per month and the cost of unit shortage is Rs. 3.20 per month. Determine the optimum stock level which minimizes the total expected cost.

RF-4804]    6    [ 400 ]







Attachment:

( 0 Votes )

Add comment


Security code
Refresh

Earning:   Approval pending.
You are here: PAPER Veer Narmad South Gujarat University 2010-2nd Sem M.C.A Computer Based Optimization Techniques : , , - - Question Paper