University of Pune 2010-2nd Sem B.E Electrical Engineering Project management(2003 ) - Question Paper
Total No. of Questions : 12] [Total No. of Pages : 2
B.E. (Electrical Engg.) (Sem. - II)
PROJECT MANAGEMENT (Elective - I) (2003 Course) (403143) (Theory)
Time : 3 Hours] [Max. Marks : 100
Instructions to candidates:
1) Section I & Section II should be solved on separate answer sheets.
2) Solve 3 questions from Section I & 3 Questions from Section II.
3) Figures to the right indicate maximum marks for the respective questions.
4) Use of scientific calculator is allowed.
SECTION - I
Q1) Elaborate the Need of Project Management? State its characteristics in Detail?
[16]
OR
Q2) Write short notes:
a) Project Life Cycle. [6]
b) Project Appraisal. [5]
c) Types of Project Organisation. [5]
Q3) Write short notes:
a) Project selection. [6]
b) Costs Associated with Project. [5]
c) Return on Investment (ROI). [5]
OR
Q4) Explain various causes of Project failure. [16]
Q5) Write short notes:
a) Critical Path Method (CPM). [6]
b) Programme Evaluation & Review Technique (PERT). [6]
c) Graphical Evaluation & Review Technique (GERT). [6]
Q6) Write short notes:
a) Gantt chart. [6]
b) Activity on Arrow Diagram (AOA). [6]
c) Activity on mode (AON). [6]
Q7) Define Material Management? Explain its functions & objectives? [16]
OR
Q8) Write short notes:
a) Purchase cycle. [6]
b) 5 Rs of Purchasing. [5]
c) Vendor Rating. [5]
Q9) Write short notes:
a) Selective Control of Inventories. [6]
b) E.O.Q. with discounts. [5]
c) Inventory of Finished goods. [5]
OR
Q10)Explain the Meaning & Importance of stores Management in detail. [16]
Q11)What do you mean by Tendering? Explain its importance? Explain various Types of Tenders with suitable examples. [18]
OR
Q12)Write short notes:
a) Risk management. [6]
b) Adjusted discount rate Method of Risk. [6]
c) Capital Asset Pricing Model (CAPM). [6]
[3764]-208 2