University of Pune 2010-2nd Sem B.E Electrical Engineering Project management(2003 ) - Question Paper

Monday, 22 April 2013 06:20Web



Total No. of Questions : 12]    [Total No. of Pages : 2

P1471    [3764]-208

B.E. (Electrical Engg.) (Sem. - II)

PROJECT MANAGEMENT (Elective - I) (2003 Course) (403143) (Theory)

Time : 3 Hours]    [Max. Marks : 100

Instructions to candidates:

1)    Section I & Section II should be solved on separate answer sheets.

2)    Solve 3 questions from Section I & 3 Questions from Section II.

3)    Figures to the right indicate maximum marks for the respective questions.

4)    Use of scientific calculator is allowed.

SECTION - I

Q1) Elaborate the Need of Project Management? State its characteristics in Detail?

[16]

OR

Q2) Write short notes:

a)    Project Life Cycle.    [6]

b)    Project Appraisal.    [5]

c)    Types of Project Organisation.    [5]

Q3) Write short notes:

a)    Project selection.    [6]

b)    Costs Associated with Project.    [5]

c)    Return on Investment (ROI).    [5]

OR

Q4) Explain various causes of Project failure.    [16]

Q5) Write short notes:

a)    Critical Path Method (CPM).    [6]

b)    Programme Evaluation & Review Technique (PERT).    [6]

c)    Graphical Evaluation & Review Technique (GERT).    [6]

Q6) Write short notes:

a)    Gantt chart.    [6]

b)    Activity on Arrow Diagram (AOA).    [6]

c)    Activity on mode (AON).    [6]

SECTION - II

Q7) Define Material Management? Explain its functions & objectives? [16]

OR

Q8) Write short notes:

a)    Purchase cycle.    [6]

b)    5 Rs of Purchasing.    [5]

c)    Vendor Rating.    [5]

Q9) Write short notes:

a)    Selective Control of Inventories.    [6]

b)    E.O.Q. with discounts.    [5]

c)    Inventory of Finished goods.    [5]

OR

Q10)Explain the Meaning & Importance of stores Management in detail. [16]

Q11)What do you mean by Tendering? Explain its importance? Explain various Types of Tenders with suitable examples.    [18]

OR

Q12)Write short notes:

a)    Risk management.    [6]

b)    Adjusted discount rate Method of Risk.    [6]

c)    Capital Asset Pricing Model (CAPM).    [6]



[3764]-208    2